Building Law Monthly
Failure to take account of early possession did not render clause a penalty
In
Eco World – Ballymore Embassy Gardens Ltd v Dobler UK Ltd [2021] EWHC 2207 (TCC) O’Farrell J held that an agreed damages clause in a construction contract was valid and enforceable
notwithstanding the fact that the contract contained no mechanism to reduce the level of liquidated damages payable to reflect
the fact that the claimant employer had taken early possession of part of the site. The sum payable was not extravagant, exorbitant
or unconscionable in amount nor was it disproportionate when considered in the light of the legitimate interest of the claimant
in the enforcement of the primary obligation of the contractor to complete the works in accordance with the terms of the contract.
However, even if the clause had been invalid as a penalty clause, it would nevertheless have operated to place a cap on the
liability of the defendant in damages in respect of the delay because the clause was drafted both as a limitation clause and
an agreed damages clause. The fact that the latter function of the clause was ineffective did not have the necessary effect
of rendering the former ineffective.