TRIPLE POINT TECHNOLOGY INC v PTT PUBLIC COMPANY LTD
[2019] BLR Plus 25
COURT OF APPEAL (CIVIL COURT)
Before Lord Justice Lewison, Lord Justice Floyd, and Sir Rupert Jackson
Liquidated damages for delay where work not completed - Damages a penalty - Operation of liquidated damages provision after termination - Operation of contractual cap on damages - Meaning of exclusion from operation of cap of liability resulting from "negligence".