TRIPLE POINT TECHNOLOGY INC v PTT PUBLIC COMPANY LTD
                                                                    [2019] BLR Plus 25
                                                                    COURT OF APPEAL (CIVIL COURT)
                                                                    Before Lord Justice Lewison, Lord Justice Floyd, and Sir Rupert Jackson
                                                                    Liquidated damages for delay where work not completed - Damages a penalty - Operation of liquidated damages provision after termination - Operation of contractual cap on damages - Meaning of exclusion from operation of cap of liability resulting from "negligence".