i-law

Building Law Reports

MAC-JORDAN CONSTRUCTION Ltd v BROOKMOUNT EROSTIN Ltd (in administrative receivership)

(1992) 56 BLR 1

Contract - Retention - JCT contract with contractors’ design, 1981 edition, clause 30.4.2.1 - Failure to place retention monies in separate account - Crystallisation of bank charge following receivership - Whether right to retention takes priority over floating charge - Whether injunction available to enforce right to retention.

THE CHANNEL TUNNEL GROUP Ltd and Another v BALFOUR BEATTY CONSTRUCTION Ltd and Others

(1992) 56 BLR 18

Arbitration - Arbitration Act 1975 section 1 - Whether stay available before pre-arbitration dispute resolution proceedings completed Injunction - Arbitration Act 1950 section 12(6)h - Power to grant injunction when proceedings stayed - Jurisdiction to grant injunction when foreign element to arbitration

Injunction - Supreme Court Act 1981, section 37 - Whether power to grant injunction where arbitration heard abroad - Effect of Civil Jurisdiction and Judgments Act 1982 section 25

ENCO CIVIL ENGINEERING Ltd v ZEUS INTERNATIONAL DEVELOPMENT Ltd

(1992) 56 BLR 43

Contract - ICE Conditions, 5th Edition, clauses 60(2) and 66 - When certified sum due

Practice - RSC Order 14 - Whether judgment possible for certified sum if amount subject to review by engineer under clause 66. Arbitration - Arbitration Act, section 4 - ICE Conditions, clause 66- Whether stay available before dispute referable to arbitration - “Matter agreed to be referred”

LESSER DESIGN & BUILD Ltd v UNIVERSITY OF SURREY

(1992) 56 BLR 57

Arbitration - Jurisdiction of the arbitrator - Reference to arbitration - Construction of reference

FAIRCLOUGH BUILDING Ltd v VALE OF BELVOIR SUPERSTORE Ltd

(1992) 56 BLR 74

Arbitration - Appeal - Error of arbitrator in rejecting uncontested claim for apparent want of proof of documents -Proper application of rules of evidence - Error in failing to inform claimants of doubts - Errors in rejecting implied terms and claims for damages - Contract - JCT Conditions, 1980 Edition, clause 26.6

ENGLISH INDUSTRIAL ESTATES CORPORATION v KIER CONSTRUCTION Ltd ENGLISH INDUSTRIAL ESTATES CORPORATION v MOSS CONSTRUCTION NORTHERN Ltd

(1992) 56 BLR 93

Arbitration - Appeal - Civil Engineering Contract -ICE Conditions, 5th Edition - Whether restriction on contractor’s option a variation - Proper value of such a variation - Effect of instruction to contractor not reaching site staff.

THE CHESTER GROSVENOR HOTEL COMPANY Ltd v ALFRED McALPINE MANAGEMENT Ltd and Others

(1992) 56 BLR 115

Contract - Management Contract - Exclusion clause - Unfair Contract Terms Act 1977, section 3(1) - Whether employer “dealing as a consumer” - Whether contract “standard terms of business” - Whether clause satisfied test of reasonableness

Copyright © 2024 Maritime Insights & Intelligence Limited. Maritime Insights & Intelligence Limited is registered in England and Wales with company number 13831625 and address 5th Floor, 10 St Bride Street, London, EC4A 4AD, United Kingdom. Lloyd's List Intelligence is a trading name of Maritime Insights & Intelligence Limited.