Professional Negligence in Construction
Page 171
CHAPTER 9
Dispute resolution
Dispute resolution
- Section A: informal dispute resolution 171
- Section B: alternative dispute resolution 172
- Section C: adjudication 174
- Section D: the pre-action protocol 176
- Section E: litigation 181
- Section F: arbitration 184
Section A: informal dispute resolution
9.1 Subject to obtaining the agreement of its professional indemnity insurer where required, there is no reason why a construction professional should not resolve a modest dispute which may raise possible professional negligence informally. 9.2 During the course of any project it is common for clients and the construction professionals they engage to differ over events that have occurred or costs that have been incurred. Such differences are generally resolved on the project or shortly afterwards in discussions. It is not uncommon for construction professionals to enter into discussions about their fees and charges when unpaid and for the client to use actual or potential errors on the part of the construction professional as a tool in negotiations. Plainly commercial life would be very difficult for any construction professional which felt prevented from making sensible agreements on small matters in order to prevent the emergence of larger dispute. 9.3 Many professional organisations require their members to provide a means for resolving complaints. Thus for example the ARB Code of Conduct provides:- 10.1 You are expected to have a written procedure for the handling of complaints which will be in accordance with the Code and published guidance.
- 10.2 Complaints should be handled courteously and promptly at every stage, and as far as practicable in accordance with the following time scales: a) an acknowledgement within 10 working days from the receipt of a complaint; and b) a response addressing the issues raised in the initial letter of complaint within 30 working days from its receipt.
- 10.3 If appropriate, you should encourage alternative methods of dispute resolution, such as mediation or conciliation.1
Page 172
Section B: alternative dispute resolution
9.7 Alternative Dispute Resolution, or “ADR”, refers to a formal process by which two parties can resolve a dispute without involving litigation. For these purposes it is also used as an alternative to adjudication and arbitration, however it its wider coinage the term can apply to almost any system of compromising claims which exists outside of the courts. 9.8 There are a multiplicity of forms of ADR, but for the purposes of claims against construction professionals, mediation is almost universally the preferred route. 9.9 Mediation is a voluntary process under which parties engage a mediator to act as a facilitator of settlement. The mediator – a neutral person, often a lawyer or another construction professional – will spend a day or longer with the parties exploring the dispute and the options for settlement. 9.10 The entire process of mediation is protected by strict confidentiality so that nothing that transpires can be used in subsequent proceeding without the agreement of the parties. If the parties reach agreement the agreement itself can become a “public” document, although here too the parties have complete autonomy. As with all the other characteristics of the process, the way in which an agreement becomes binding and the use that may be made of it is regulated by the agreement which the parties have signed so such variation as they may agree. There is no limit on the number of parties to a mediation and indeed the process is particularly successful in comparison with other forms of dispute resolution when it comes to resolving multi-party disputes. 9.11 Some professional bodies expressly endorse mediation as a means of dealing with disputes against construction professionals,2 but it is very widespread as a tool by whichPage 173
Page 174
Section C: adjudication
9.20 Most construction professionals will be familiar with adjudication. In the United Kingdom it is a process of dispute resolution introduced by Parliament4 and intended to provide speedy interim decisions in relation to (mostly) disputes about payment. Parties to “construction contracts” must include provisions for adjudication in the contract and in default of compliant provisions a statutory scheme will be implied. 9.21 The legislative intent is to provide a means whereby disputes could be resolved by an impartial adjudicator, generally within 28 days, whose decision would be binding upon the parties until overturned (or confirmed) in court or arbitration. 9.22 The genesis of the scheme was concern that larger construction companies were exploiting smaller ones by delaying payments due (or in some cases simply not paying at all), taking advantage of the fact that there was no speedy and cheap means by which they could be made to meet their obligations. It seems unlikely that Parliament had disputes involving construction professionals uppermost in its mind when it passed the Act. However, its provisions are very broad and the definition of “construction contract” and “construction operations” are sufficiently widely drawn to encompass almost all contracts between construction professionals and their clients, including collateral warranties.5 9.23 Construction professionals who act at a remove from the works themselves may fall outside the Act (for example the provision of expert or other evidence)6 but the provision of services in relation to ongoing construction works will almost always fall within it. The only exception is contracts with the occupiers of residential dwellings (private houses or flats), which are excluded from the scheme.7Page 175
Page 176
Section D: the pre-action protocol
9.32 In the United Kingdom the courts encourage prospective parties to litigation to explore those claims in correspondence before proceedings are issued. The process aimed at facilitating settlement and narrowing areas of dispute so that if proceedings are issued costs and time are not wasted dealing with irrelevant or unnecessary issues. 9.33 Court encouragement of the process has led to the development of formal protocols to guide the pre-action process. Whilst there is a separate protocol for professional negligence claims, disputes involving construction professionals fall to be dealt with under the Pre-Action Protocol for Construction and Engineering Disputes.21 9.34 Failure to follow the Protocol without good reason may result in adverse award of costs in subsequent court proceedings. Whilst the use of this Protocol is not generallyPage 177
Page 178
Within 21 days after receipt by the Claimant of the Defendant’s letter of response, or (if the Claimant intends to respond to the Counterclaim) after receipt by the Defendant of the Claimant’s letter of response to the Counterclaim, the parties should normally meet.