Litigation in the Technology and Construction Court
Page 89
CHAPTER 6
Defects claims
General nature of a defects claim
6.1 Conceptually, defects claims are very wide-ranging indeed. To the layman, a ‘defect’ will usually comprise some physical deficiency in the completed works, such as a leaking roof, or ill-fitting floorboards. Conversely, there may be nothing physically wrong with a structure, yet it is still ‘defective’ – for example, a building which is watertight yet has been finished in the wrong render (contrary to an agreed specification), or a door which has been painted in the wrong colour (against an employer’s instructions). Some buildings may exhibit signs of physical ‘defects’ which are not in fact attributable to any underlying breach, the classic example being shrinkage cracks in a large concrete slab, which generally speaking are unavoidable. 6.2 Matters become complicated when defects emerge which are not readily attributable to any particular cause (for example, a warehouse floor which is suffering from cracking). Time and time again the same story emerges: the design and build contractor asserts that such cracks are down to shrinkage, and usually passes all of the claims down the line without offering up any properly substantiated defence; the slab subcontractor blames the foundations subcontractor; and the foundations subcontractor blames the slab subcontractor. The employer, of course, blames everyone, only to then find himself criticised for inadequate maintenance, or unrealistic expectations when it comes to the scope of the necessary remedial scheme. 6.3 Every construction practitioner will have come across defects claims. For some, they will be a bread-and-butter part of practice. Many litigators loathe them, and even the most energetic lawyer is unlikely to be particularly enthused by their study; see, for example, the first paragraph of the recent case of Manorshow Ltd v Boots Opticians:1 ‘This is a dilapidations claim.’ 6.4 That said, defects claims form a central part of TCC business, and long will they continue to do so. Notwithstanding better design and construction teams, together with more efficient management and quality control, the human element in the process of construction means that defects are inevitable. As projects become larger and more complicated, sucking in construction professionals and consultants as well as contractors and their subcontractors, multi-party disputes are commonplace, and at times even the physical capacity of the Rolls Building Courts to accommodate the hearing is tested. In such circumstances, efficient management of such litigation is an important part of the TCC’s role. 6.5 One of the difficulties in writing a chapter of this sort is the general absence of any reported cases concerning the case management and presentation of such claims. As to case management, almost all of the important procedural decisions are made at CMC stage, withPage 90
Prosecuting a defects claim
Structure of the statement of case
6.7 There is no right or wrong way to plead out a defects claim. Much will depend on the nature of the problems in question. For example, it may be apparent from an early stage that liability will not be a large issue in dispute, but scope of remedial works will be, in which case the primary focus of the draftsman may be on schemes of remediation, in telling the story as to how attempts to repair have failed, or in highlighting the intransigence of the defendants in attending to the problems. In other instances, liability will be hotly contested, but quantum more or less agreed. 6.8 There are, therefore, no hard and fast rules, but it is submitted that the following is a sensible structure which can be adapted as appropriate to suit the relevant dispute:- The parties. Who to sue will be driven by a variety of considerations. A design and build contractor with full design responsibility will often suffice, but there may be a need to bring in further parties (such as subcontractors under warranties, or consultant professionals under warranties or in tort) in the event of a lack of insurance, parlous financial circumstances or even out of an abundance of caution, especially where knowledge of the claim is not as advanced as it might be.
- Obligations. This includes all relevant contracts and/or appointments and/or duties of care. Where contractual obligations are relied upon, and where appropriate, the scope of the relevant obligations should be identified. Often, documents such as the Employer’s Requirements, or specifications, or even standalone express terms of the contract itself, will import fitness for purpose obligations, or other sorts of ‘absolute’ obligations or performance requirements, which may be unfettered by the normal obligation to take reasonable skill and care (whether express or implied). Aside from express ‘fitness for purpose’ obligations, such requirements might include obligations for a floor to take particular loadings, for a process plant to meet specified output parameters or for a building to satisfy a certain ‘design life’ or ‘service life’. To this end see, for example, MT Hojgaard AS v E.ON Climate and Renewables UK Robin Rigg East Ltd 2 and 125 OBS (Nominees1) Ltd v Lend Lease Construction (Europe) Ltd.3 Contracts of this sort are often termed contracts of ‘double obligation’ and are a very powerful weapon to the claimant, as where absolute requirements can be made out, the reason why the requirements have not been satisfied is usually irrelevant.
-
Page 91
- Identification of the defects, including a narrative of how and when they emerged or were discovered, together with any reaction to them and/or involvement in remedials/attempted remedials by the defendants. The reaction of particular defendants in these periods may well prove important in the event that a limitation defence is subsequently advanced, as sometimes the conduct of parties may operate so as to extend time for limitation purposes.
- Breach. These allegations should be set out ‘hierarchically’. For example, where there are breaches of fitness for purpose obligations, or failures to meet any other absolute performance requirements, these breaches should logically be pleaded out first. Following those should be any further breaches of express or implied terms of the contract. In defects claims, these breaches will usually comprise: (1) failure to comply with express obligations set out in contract documents; or (2) failure to comply with any express or implied obligation to carry out works or services with reasonable skill and care (or any analogous wording). Normally, the breaches can be categorised thematically, and it is submitted that it is good practice to do so, importing sub-headings and signposting wherever possible. Such categories will usually include: (1) defective design/specification; (2) defective workmanship; and (3) defective materials. Depending on the problems in question, there may be room for other residual breaches (for example, failures to warn). Often, it will be necessary to work backwards from each of the defects to identify the relevant operative breach(es) of contract and/or duty. Only operative breaches should ever be pleaded. Where alleging breach, and in particular breaches of the obligation to carry out works with reasonable skill and care, the draftsman should always identify (1) the steps which were taken but should not have been and (2) the steps which were not taken but should have been. Simply asserting that a defendant was in breach for either doing something or not doing something is an incomplete allegation and will be countered by any sensible defendant with a request for further particulars.
-
Factual/technical causation of the defect. This section should set out a description of how each of the breaches in question have caused and/or contributed to each of the defects in question. This is usually the most difficult and lengthy section of any defects statement of claim. Drafting it will often entail a detailed understanding and explanation as to how, for example, a breach led to particular forces or stresses being exerted on particular parts of the structure, such forces and/ or stresses then being the cause of particular physical damage. Sometimes more
Page 92
- Legal causation. This section should explain how each of the breaches has caused and/or contributed to each of the losses in question, which will normally entail a description of how the defects have led to the need to remediate and/or a diminution in value of the asset. This section can usually be relatively concise, as tying in each of the defects to the breach(es) in question will have already been accomplished in the ‘causation of the defect’ section above.
- Loss. For a claimant, this will normally be the costs of reinstatement together with ancillary claims (for example, loss of rent, business disruption, wasted management time, professional fees, etc). In some instances, this section may need to include material anticipating and refuting any allegations of a failure to mitigate loss. One important tactical consideration for a claimant at this stage is whether or not to plead alternative remedial schemes, particularly where lesser or cheaper proposals have been historically advanced by the defendants. It is submitted that where proposals have been put forward, and they are unfeasible for technical or other reasons, claimants should deal with them upfront, even if further detail needs to follow in the Reply. Where the issue becomes a particularly acute consideration, however, is where limitation is in issue: see, for example, Cooperative Group Ltd v Birse Developments Ltd,4 where the Court of Appeal had refused an earlier attempt to amend pleadings concerning the appropriate remedial scheme, and a further attempt to amend was refused on the basis that the claimant could and should have pleaded its true case much earlier in the proceedings. Where limitation is looming, one practical consideration might be to append a list of all facts and matters known to the claimant in relation to both the construction of the property and the defects, and to require the defendants to plead to it, so at the very least, there is a good chance that all relevant facts and matters concerning the problems will be the subject of the parties’ pleaded cases, thus (with a fair wind) removing, or at least lessening, the risk that amendments to introduce and rely on alternative schemes will be refused on the basis that they do not arise out of the facts and matters in issue between the parties (any claim arising out of ‘new’ facts and matters being time-barred). The safest option, however, is always to plead properly and fully first time around.
Page 93
Defending the case
Liability defences
6.10 The starting point for any defendant is to resist a claim on the basis that breach is either not made out or any breach did not cause the damage complained of. 6.11 For contractual claims, building contracts frequently contain a myriad of obligations, some of which, on analysis, are conflicting, or incorporate performance requirements which are somewhat opaque (again, see MT Hojgaard). It may be that the obligations asserted by a claimant are not as extensive as the claimant might like, or that what are alleged to be performance requirements are in fact subject to some dilution (for example, being limited to the operation of a reasonable skill and care as opposed to the satisfaction of an absolute obligation). 6.12 To this end, there really is no substitute for careful analysis of all relevant contract documentation, which may (in the case of historic claims) necessitate disclosure requests from the claimant in order to obtain full copies of the contract itself. 6.13 Where the documentation does not reveal the existence of a stand-out contractual defence, investigation of the specific allegations with the assistance of experts is crucial. At the very least, this may give rise to the opportunity to pull in other parties by way of contribution proceedings – for example, if it transpires that the failure of a particular element can be attributed to both design and workmanship deficiencies. 6.14 Further, where claims are brought against construction professionals, the terms of the relevant appointment are, of course, paramount, and increasingly often will contain express limitations on liability, or net contribution clauses. The latter in particular may well give rise to a powerful defence even if breach cannot realistically be defended.Quantum defences
6.15 In defects claims, quantum defences usually focus on two issues, namely that (1) the pleaded remedial scheme is disproportionate or otherwise excessive or (2) the claimant has failed to mitigate its loss. 6.16 Rival remedial schemes are almost inevitable where the claimed remedial scheme is extensive. They should, however, be investigated carefully, and ought not to be put forward where they are technically doubtful (see, for example, the Court’s rejection of ‘resin jacking’ as a viable remedial scheme to a sinking floor slab in Cooperative Group Ltd v John Allen Associates Ltd).5 6.17 The credibility of any rival remedial scheme will, it is submitted, also suffer in the event that it is put forward in a defence either (1) as part of a large menu of alternative options or (2) without any adequate particulars. The first tends to suggest a certain level of desperation, and the latter a lack of belief in the suitability of the proposed solution.Page 94
Limitation
6.21 One factor of which defendants should be acutely aware at all times is the possibility of a limitation defence. Many defects claims, particularly those involving multiple parties or those concerning chronic failures manifesting themselves over a long period of time, are by their nature pretty sterile, and often litigation is a last resort embarked upon to prevent claims becoming time-barred. Even then, deadlines are often missed. Indicators of potential weaknesses in a claimant’s case in this regard might include reliance on a duty of care in tort (in an attempt to extend time to the date of damage, as opposed to the date of breach), or as intimated above, vague or woolly pleading concerning the dates upon which work or services were carried out and/or completed. Avenues for limitation defences may also appear where deeds are improperly executed or delivered. 6.22 Defendants should always be alert to the possibility of running such defences and should not treat the claimant’s pleaded case as gospel. Further, in tort in particular, the case law in relation to limitation continues to develop (see, for example, Coop v Birse,9 in which it was held that a contractor’s cause of action in tort against its subcontractors accrued on the date of practical completion, when the building was handed over by the contractor toPage 95
Controlling, policing and challenging the presentation of defects claims
6.24 Defects claims frequently suffer from inadequate particularisation. There are many reasons for this: sometimes claims are issued in a rush, on account of limitation deadlines or other commercial considerations; on other occasions, the draftsman may lack sufficient information and/or an understanding as to the level of detail which is required to properly articulate a complicated claim for breach of contract. 6.25 A common occurrence in this regard is the eliding of the concepts of breach of contract on one hand and defects on the other. A defect, of course, is the physical manifestation of a breach or breaches of contract. But the breach still needs to be identified. All too frequently, defendants find themselves defending what is no more than a list of defects (and often a rudimentary one at that) which is presented as particulars of breach. In fact, that list is no more than what presumably it was originally intended to be, namely a list of problems with a building or facility. Such lists often disclose no discernible cause of action. 6.26 Another familiar tactic is to attach a schedule or report to the relevant pleading, usually one which has been prepared by a professional of sorts, and often for negotiation purposes. The report is then offered up in lieu of providing proper particulars of breach and/or causation, presumably from a (misguided) perception that costs can be saved in this way. 6.27 Finally, there will always be claimants who cut corners when it comes to pleading causation, leaving the defendant to unpick a generalised allegation such as ‘The defects below were caused and/or contributed to by the breaches set out above’, which is self-evidently unhelpful, but nevertheless commonplace. 6.28 Such practices have the potential to drive up unnecessary cost if they are not dealt with swiftly and robustly. The obvious time to do so formally is at the CMC, but it is submitted that the party facing a poorly articulated claim ought to prepare itself early by:- issuing correspondence pointing out the failings in question and putting that party on notice in relation to costs (and this is the very least that should be done);
-
Page 96
- trying the highest value items and agreeing a process of pro rata extrapolation across the remainder;
- picking items at random and again agreeing a process of pro rata extrapolation across the remainder; and
- grouping defects into categories and trying a particular item or items in that category (again with some form of extrapolation across the remainder).
Instructing appropriate expertise
Appointment of experts
6.34 Expert evidence has been dealt with generally in . In this section, specific issues relating to expert evidence in defects cases are discussed. 6.35 Defects claims have a tendency to draw in a multiplicity of experts, with disciplines seemingly endless and ever more esoteric. That said, in the post-Jackson era, withPage 97
- consideration of a jointly instructed expert or experts, particularly where there are multiple defendants who might usefully combine resources on specific issues (such as, for example, the sharing of valuation experts by defendants facing claims for diminution in value in the alternative to the costs of reinstatement);
- agreeing to dispense with quantum expert evidence and instead to source commercial quotations for particular remedial works;
- requesting liberty to apply at a later stage for expert evidence in a particular discipline in the event that it turns out to be required, its necessity not being readily apparent at CMC stage when the dispute is still relatively nascent; and
- appointing an expert who is capable of opining in more than one discipline, particularly where there is an overlap (as may be the case with disputes concerning both geotechnical and structural engineering, for example).