Litigation in the Technology and Construction Court
Page 99
CHAPTER 7
Public procurement litigation in the TCC
Introduction
7.1 Procurement litigation is fast-moving and often somewhat fraught. The short time limit in which to bring claims (in most cases, 30 days from the date on which the claimant first knew or ought to have known of the facts amounting to breach)1 and the somewhat one-sided nature of the process (whereby contracting authorities tend to hold the vast majority of disclosable information) mean that much Court time relating to procurement challenges is taken up with interlocutory applications, often prior to close of pleadings. 7.2 Applications by economic operators (typically for disclosure) are frequently met with cross-applications by authorities (typically for relief from the automatic injunction under Regulation 95(1), further information and strike out/summary judgment (often on limitation grounds)). Very few cases make it all the way to trial, but over the past six or seven years, the TCC has heard a growing number of cases in relation to public procurement challenges. 7.3 As a result, the TCC can now genuinely hold itself out as a pre-eminent Tribunal for the consideration of both final and interlocutory matters in the field. This reputation has recently been enhanced by the publication of the TCC Guidance Note on Procedures for Public Procurement Cases, launched in July 2017, and which now appears at Appendix H to the TCC Guide. Although it is described as guidance as opposed to a protocol, it is expected that it will be adopted in all procurement disputes going forward. A copy of the protocol is appended at hereto. 7.4 A notable feature of procurement litigation is the ever-changing statutory regime pursuant to which claims are brought, namely the Public Contracts Regulations. At the time of writing, the 2015 Regulations are in force, which are the fourth iteration of the relevant legislation in the past 12 years. As well as keeping lawyers on their toes, the frequent revisions in the law introduce new concepts, many of which are relatively untested in litigation (e.g. the concept of ‘ineffectiveness’ introduced by the 2009 Regulations, and the codification of European jurisprudence in relation to ‘material change’ enshrined in the 2015 Regulations). 7.5 The 2016 referendum in the United Kingdom, which saw a majority of the British population vote to leave the European Union, imports further uncertainty over the direction in which the law might develop. To the editors, at least, it seems somewhat implausible that competitive tendering as a concept will be abandoned, not least on account of the fiduciary duties of public bodies, but also given that both contracting authorities and contractors have well-established processes for participating in competitions. Depending on the naturePage 100
Applications to lift the automatic suspension
7.7 Prior to the coming into force of the Public Contracts (Amendment) Regulations 2009 which implemented the new Remedies Directive (2007/66), an aggrieved economic operator who wished to stop a procurement process (and thereby prevent contract award) needed to apply for an interim injunction. 7.8 Under the 2006 Regulations, the Courts approached the question of whether or not to grant an order restraining a contracting authority from entering into a contract by applying the test for an interim injunction set out in American Cyanamid Co Ltd v Ethicon Ltd 2, by considering: (1) if there is a serious issue to be tried; (2) if an award of damages would be an adequate remedy for the claimant if no injunction were granted; and (3) where the balance of convenience lies. The Court’s application of the American Cyanamid test in procurement cases is a developing area of jurisprudence, with some Judges maintaining the three-stage analysis set out in American Cyanamid itself, while others take the view that the adequacy of an award of damages falls to be considered as part of the balance of convenience, which is likely to include the adequacy for the defendant of any cross-undertaking offered and protection of the public interest. 7.9 From the perspective of the aggrieved contractor who had missed out on the contract, the ‘old’ regime posed a practical problem: contracting authorities who became aware of an injunction application would immediately award the contract, leaving the challenger with a remedy in damages only. This became known as the ‘race to contract’ or ‘race to signature’. The European Commission became concerned that: (1) contracts were being awarded before Tribunals had the chance to consider applications for injunctive relief (see the May 2006 impact assessment report (COM(2006)195); and (2) contracts were being awarded illegally, while the existing regime did not make it possible to prevent or correctPage 101
Page 102
- In Counted4 Community Interest Co v Sunderland City Council,7 the first decision under the 2015 Regulations, the Court held that damages would not be an adequate remedy for the claimant: if the suspension were lifted, then the workforce would be lost and it would take years to develop skills which were not available on the wider market. Further, the current service being supplied for the duration of the suspension did not create a risk to users of the service such that the public interest outweighed the prejudice to the claimant if the suspension were lifted.
- In Bristol Missing Link Ltd v Bristol City Council,8 damages were held not to be an adequate remedy because the claimant was a non-profit-making organisation and lifting the suspension would have caused it to lose a third of its turnover, which would have had a knock-on effect on the other services it provided. If the
Page 103
- In NATS (Services) Ltd v Gatwick Airport Ltd,9 the injunction was upheld because there would have been great difficulty in estimating the damages, and further the loss of the contract would have significantly impaired NATS’s ability to secure international air traffic control contracts. There had already been a significant delay in the procurement process and a further delay had to be seen in that context. The authority’s resulting position of uncertainty was not determinative in the balance of convenience.
- In DWF LLP v Secretary of State for Business, Innovation and Skills,10 the Court of Appeal lifted the injunction with regard to all successful bidders except those with whom DWF had originally tied for last place. If DWF won at trial, damages would not be an adequate remedy because they would be impossible to quantify fairly. By contrast, if DWF lost, then the Secretary of State’s damages would be easily quantified.
- Particularly where the suspension is maintained, the TCC is likely to support and impose a rapid progress to trial (and may well use powers to control and define the scope of disclosure in such cases – as to which see below). For the consideration of expedition principles before contract award, see Joseph Gleave v Secretary of State for Defence.11
- For economic operators, serious consideration should be given to whether or not the application brought by the authority to lift the suspension should even be contested. Starting proceedings (and the imposition of the injunction) does provide some commercial clout to a contractor looking to negotiate a solution, but the bulk of the jurisprudence suggests that this will be a hurdle which, more often than not, is overcome by the authority, with consequent costs sanctions imposed on the contractor (and the morale-boosting effect of an early win) if the application is contested. Moreover, consenting to the termination of the suspension may signal to the defendant that the claimant has confidence in their case.
- There are circumstances where money alone will not offer an adequate remedy due to other consequences stemming from the contract being awarded to another party – for example, redundancies, loss of human capital through TUPE transfers, loss of market share or loss of reputation (see the remarks of the Court in John Sisk & Son Holdings Ltd v Wester Health and Social Care Trust
12 (although the injunction was lifted in that case)). If contractors wish to contest applications, then these are
Page 104
- Authorities should make the application early. Given the TCC’s willingness to accommodate expedited trials, a late application may well be met by the submission that the balance of convenience militates against the injunction being lifted because: (1) most procurements are usually fairly long in the tooth by the stage that litigation is commenced; (2) the authority has delayed in making the application; (3) the Court is able to fix a hearing in a relatively short space of time; and (4) there is no discernible prejudice to the authority in waiting a few weeks or months longer for the conclusion of a trial and handing down of judgment before being permitted (or not) to award the contract in question.
- If authorities are sensitive about disclosure (as to which, see below), it is unwise to take the point that there is no serious issue to be tried unless the claimant’s case is clearly unsustainable on its face, without the need for evidence. The requirement that there be a serious issue is sometimes described as a low threshold, so in most cases (but not all, as identified in the cases cited above) the claimant will satisfy the requirement; an assertion that there is no serious issue may attract a successful application for early specific disclosure so that the contractor can rebut the allegation. Many authorities, ultimately, will concede the point (even if the concession is not made until exchange of skeleton arguments) rather than risk being ordered to provide documents that they would rather hold back for the time being. It is submitted that this is a sensible approach (apart from in the most extreme cases where the challenge is fanciful) and consistent with authority. For example, in Pearson Driving Assessments Ltd v The Minister for the Cabinet and The Secretary of State for Transport,13 the Court considered an application for early specific disclosure in the context of a pending section 47(H). At paragraph 15, the judgment states:
The court, on the application of Section 47 (H), will simply not be in a position to find facts which are controversial or at the very least, which are not supported clearly by uncontroversial, contemporaneous documentation. Therefore, insofar as there is reliance by the defendants on those sorts of facts, those are facts which cannot properly be deployed as grounds for deciding that there is no serious issue to be tried.