Adjudication in Construction Law
Page 433
CHAPTER 9
Contractual adjudication
9.1 Introduction
9.1 As has been observed above,1 the origin of adjudication in relation to construction contracts lies in the inclusion in standard forms of construction sub-contracts during the 1970s of provisions for an ‘adjudicator’ to decide disputes between the sub-contractor and the main contractor as to the entitlement to payment pending a final resolution by arbitration. Part II of the Housing Grants, Construction and Regeneration Act 1996 confers on a party to a construction contract the right to refer a dispute arising under the contract for adjudication under a procedure complying with section 108.2 It is only if the contract does not contain in writing the provisions required by section 108 that the adjudication provisions of the Scheme for Construction Contracts apply.3 It therefore remains open to parties to construction contracts covered by Part II to include their own adjudication provisions provided that they are compliant with the statutory requirements.Page 434
9.2 JCT adjudication provisions
9.3 With three exceptions, the widely used Joint Contracts Tribunal (JCT) standard forms of building contract now simply provide that the Scheme for Construction Contracts is to apply.4 The exceptions are the JCT Building contract for a home owner/occupier who has appointed a consultant to oversee the work (HO/C), the JCT Consultancy agreement for a home owner/occupier appointing a consultant in relation to building work (HO/CA) and the Building contract for a home owner/occupier who has not appointed a consultant to oversee the work (HO/B) 2005 (revised July 2009; revised March 2015), construction contracts with a residential occupier not being subject to Part II.5 The Royal Institution of Chartered Surveyors (RICS) and the Joint Contracts Tribunal Ltd publish rules for use with these forms.6 An adjudicator under them can be appointed by the Royal Institution of Chartered Surveyors, the Royal Institute of British Architects (RIBA) or the National Specialist Contractors Council (NSCC).7 If the dispute is about payment, the adjudicator can order the customer to pay the contractor, with interest, any amount which he or she decides is appropriate. The adjudicator can also order the contractor to repay the customer, with interest, any money which he or she decides is appropriate. The rate of interest will be no more than 5% per annum above the official dealing rate of the Bank of England current at the date when the adjudicator considers that interest should apply and will run for such period as the adjudicator thinks fit.8 The adjudicator is not required to give reasons for his or her decision.9 The customer and the contractor must follow the adjudicator's decision as part of their obligations under the building contract, unless and until either party obtains a court judgment about the dispute which is different from the decision of the adjudicator.109.3 NEC4 contracts
9.4 The NEC4 standard forms of construction contract contain two options relating to adjudication. Where the Housing Grants, Construction and Regeneration Act 1996 (as amended) regulates the contract in question, Option W2 applies. A dispute arisingPage 435
- • The natural and ordinary meaning of the words ‘a dispute’ is a single dispute. Similarly, other sub-clauses of W2 referred to ‘a’ or ‘the’ dispute in the singular.
- • The purpose of Option W2 was clearly to give effect to the provisions of section 108 of the 1996 Act.
- • It was well understood that in the context of the Statutory Scheme only one dispute could be referred to adjudication at a time. If the authors of Option 2 had wished to take a different approach and to have multiple disputes referred at the same time, one might expect them to have made that clear in their drafting of Option 2. They did not.
- • If, in turn, the parties wished to allow the referral of multiple disputes, it was open to them to amend the standard terms. Again, they did not.
- • All that is reinforced by the fact that it made sense for the parties to have agreed that only one dispute should be referred to the adjudicator at any one time for the same reasons as under the Scheme, namely that adjudication is a fast and summary procedure that risks becoming difficult to operate if an adjudicator has to deal with multiple disputes at the same time. In turn, that falls to be weighed against the fact that the courts take a wide and commercial view of what constitutes a single dispute.
- • Whilst there is no express preclusion of the referral of multiple disputes in the contractual provisions nor is there any express inclusion of such a referral. The fact that paragraph 8(1) of the Scheme contemplates a single dispute being referred unless the parties agree otherwise is a neutral point.
- • The fact that clause W2.2(3) allows successive disputes to be referred to the same adjudicator once appointed, does not mean that multiple disputes should be referred to him or her all at the same time. On the contrary, it contemplates a series of separate adjudications.
Page 436
Page 437
Page 438
9.4 ICC (ICE) adjudication provisions
9.10 The standard forms of ICE civil engineering contracts previously published by the Institution of Civil Engineers have now been succeeded by the Infrastructure Conditions of Contract (ICC) standard forms published by the Association for Consultancy and Engineering (ACE) and the Civil Engineering Contractors Association (CECA). Under the ICC forms, the employer or the contractor may at any time by notice in writing require any dispute between them to be referred to adjudication whether or not the dispute has been referred to the engineer. The adjudicator is to be appointed as provided in the appendix to the contract and the adjudication shall be carried out in accordance with the adjudication procedure stated in the appendix.30 The adjudicator's decision is to be binding on both parties and may be enforced as provided by sub-clause 2.4.31 If either party gives written notice within 28 days of the date of the adjudicator's decision requiring the disputePage 439
9.5 GC Works contracts
9.13 Express provision is made for adjudication in the Government Standard GC Works forms of contract prepared by the Property Advisers to the Civil Estate (PACE) for major UK building and civil engineering works. They envisage that a person has been named as adjudicator in the abstract of contract particulars.41 It is a condition precedent to the appointment of an adjudicator that he or she shall notify both parties that he or she will comply with the relevant clause and its time limits.42 A copy of the notice of referral andPage 440
- • on the whole or part of any amount awarded, in respect of any period up to the date of the award;
- • on the whole or part of any amount claimed in the adjudication proceedings and outstanding at the commencement of the adjudication proceedings but paid before the award was made, in respect of any period up to the date of payment; and may award such interest from the date of the award (or any later date) until payment, on the outstanding amount of any award (including any award of interest and any award of damages and legal and other costs and expenses).47
- • decisions by or on behalf of the employer on site admittance;
- • decisions by or on behalf of the employer on passes;
- • provided that certain circumstances have arisen, and have not been waived by the employer, decisions of the employer to give notice of determination;
- • decisions or deemed decisions of the employer to determine the contract;
- • provided that certain circumstances following suspension of works have arisen, and have not been waived by the employer, decisions of the employer to give notice of determination; and
- • decisions of the employer on assignment.
Page 441
9.6 IChemE contracts
9.18 The Institution of Chemical Engineers (IChemE) produces a number of standard forms of contract relating to chemical, biochemical and process engineering works, which contain provisions for adjudication. The relevant provision in each of these forms restricted the application of the adjudication provisions to construction contracts as defined in the Housing Grants, Construction and Regeneration Act 1996 or any amendment or re-enactment of that legislation. Experience had shown that this provision increasingly gave rise to considerable uncertainty and numerous challenges to the jurisdiction of adjudicators. These, in turn, cause difficulty to the parties, their representatives and adjudicators alike.55 Accordingly, clause 47 in each of these forms was with effect from 2 March 2020 to bePage 442
9.7 Institutional procedural rules
9.7.1 Technology and Construction Bar Association (TECBAR)
9.20 Several institutions publish adjudication procedural rules independently of any standard form of construction contracts. The Technology and Construction Bar Association has published the TECBAR Adjudication Rules 2012, which incorporate the adjudication rules in the Statutory Scheme for Construction Contracts (as in force in England and Wales and as amended from time to time) and give guidance on various topics. Unless otherwise agreed, the adjudicator has no power to order one party to pay the costs incurred by the other party.609.7.2 Technology and Construction Solicitors’ Association (TeCSA)
9.21 The Technology and Construction Solicitors’ Association has issued the TeCSA Adjudication Rules – 2018 Version 3.2.2 Procedural Rules for Adjudication. The scope of the adjudication is to be the dispute identified in a written notice of adjudication givenPage 443
- • any further matters which all parties agree should be within the scope of the adjudication; and
- • any further matters which the adjudicator determines must be included in order that the adjudication may be effective and/or meaningful.61
Thus, it is a matter entirely for the adjudicator to decide which of the matters he or she will decide in the course of the adjudication. He or she has complete discretion over the scope of the adjudication and can make a decision as to what is within the scope of the adjudication. He or she has obviously to have regard to the notice, but the decision as to what is comprised within the notice is a matter which is by contract given to the adjudicator to decide.62