Lloyd's Maritime Law Newsletter
Naviagro Maritime Corp. v. SL Sethia Liners Ltd. (The Kostas Melas) - Mr. Justice Robert Goff - Q.B. - July 18, 1980
Arbitration - Interim awards for hire
The owners claimed that deductions made from hire by time charterers were unjustified and sought an interim award from arbitrators
for whatever minimum sum might be found due, before redelivery had taken place. Such an award was made. The charterers asked
the Court to set aside or remit the award.