Delay and Disruption in Construction Contracts
Page 1137
INDEX
INDEX
- Acceleration
- breach of contract 11-099
- constructive see Constructive acceleration
- costs 11-112
- culpable delay, and 11-090
- design programmes 2-102
- effect 11-019
- entitlement to extension of time, and 11-090
- estimates of cost 11-075
- failure to accelerate 11-109–11-213
- breach of obligation, 11-195, 11-196
- causation 11-199, 11-204
- compensation 11-192
- completion on time 11-192, 11-193,
- culpable delay 11-193, 11-196, 11-201, 11-202, 11-204
- demurrage claims 11-208
- foreseeable delay 11-200
- foreseeable losses 11-191–11-192
- identification of loss 11-197, 11-204
- instructed acceleration 11-189
- instructions to recover 11-198, 11-199, 11-201–11-204
- limitation on liability 11-206
- liquidated damages 11-190, 11-204–11-207
- redress 11-194, 11-196
- termination of contract 11-209–11-211
- instructed 11-068–11-071, 11-077, 11-089
- lost productivity, and 17-046–17-052
- meaning 11-015, 11-016–11-018
- methods 11-137–11-188
- power to instruct 11-088–11-090
- schedule of 4-207
- standard form provisions 11-021–11-092
- Access 4-164–4-170
- Act of God 4-055, 4-056
- Activity coding 7-232
- Activity durations 7-126–7-142
- Acts and/or omissions of developer 4-028–4-036
- Acts of State 2-149
- Acts of third parties 4-173–4-188
- Acts or omissions of third parties
- Additional work
- guidelines 12-016
- Adjudication 22-106–22-113
- final and binding 22-113
- Adjudication in United Kingdom 23-001–23-063
- complex decisions 23-003, 23-007–23-022
- costs 23-004, 23-023–23-027
- definition of construction contract 23-005, 23-038–23-044
- human rights aspects 23-003, 23-007–23-022
- interest 23-004, 23-023–23-027
- limitation periods 23-002
- recovering costs 23-063
- residential occupiers 23-045–23-047
- sequential 23-006, 23-48–23-062
- single disputes 23-006, 23-048–23-062
- Adverse weather
- Alliancing 3-060–3-063
- Alternative dispute resolution 22-087, 22-088
- Ambiguities 12-110–12-135
- American law
- Antiquities 4-264–4-266
-
Page 1138
- A/B estimates approach 20-058–20-061
- balance of evidence, 20-005
- burden of proof approach 20-042
- but-for test, 20-005
- case law 20-003, 20-004
- causation, 20-001–20-004
- City Inn approach 20-068–20-070
- common law 20-009
- compensation, and 20-010–20-012
- delay to completion 20-013–20-031
- delta estimates approach 20-062, 20-063
- Devlin approach 20-043–20-045
- dominant cause approach 20-046–20-053
- jury verdict approach 20-054, 20-055
- logical processes 20-005
- loss and/or expense 20-032–20-036
- methods of apportionment of loss or expense 20-037–20-073
- modified global claim approach 20-056, 20-057
- modified total cost approach 20-064–20-067
- nature of 20-001
- net effect approach 20-071–20-073
- prolongation issues, and 20-006, 20-007, 20-011
- tortious solution 20-040–20-041
- Approval of programmes 8-001–8-091
- Approximate bills
- Arbitration 22-114–22-118
- Arrow diagram 8-036–8-042
- Artificial obstructions 4-157
- As-built programme 7-058
- As-built schedule
- As-built impacted
- As-planned updated versus as-planned u[dated
- Assessor
- discretion of court, and 22-041
- Bar chart 8-007–8-017, 14-223–14-231
- Baseline programme 7-028–7-037
- Best endeavours
- meaning 11-037
- Biddability risk 2-113–2-124
- bills of quantities 2-115
- claims conditions 2-119
- greenfield sites 2-116
- itemised bills of quantities 2-122
- lowest tendering contractor 2-118
- manifest error 2-121
- nature of 2-113
- precision in communication 2-120
- predetermined cost and time effect of variations 2-123, 2-124
- preparation of tender documentation 2-117
- price, and 2-114
- Bill of quantities 12-075–12-109
- additional work by way of increased quantities 12-105
- biddability risk, and 2-115
- compensation for prolongation 12-080
- drawings 12-100
- importance of 12-077
- incorporation as contract document 12-109
- lump sum, and 12-078
- precedence of 12-089, 12-090
- purpose 12-076
- re-measurement of quantities 12-081
- rules of measurement 12-093
- BIM 13-067–13-119
- acronym 13-071
- case law 13-115, 13-116
- case studies 13-094–13-100
- collaboration 13-084, 13-085
- communication of information 13-113, 13-114
- conventional practice, and 13-074–13-077
- Cookham Wood 13-096–13-099
- definition 13-072, 13-073
- future projects 13-100
- investment 13-090, 13-091
- key documents 13-093
- legal, contractual and insurance issues 13-086
- levels of maturity 13-078, 13-079
- overcoming barriers 13-092
- perceived barriers against adoption 13-083
- perceived benefits 13-081, 13-082
- retrieval of information 13-111, 13-112
- significance 13-107–13-110
- standard forms of contract 13-101–13-106
- UK and management of information 13-087–13-089
- what is arguably not 13-080
- Black Monday 2-145
- Bricklaying
- calculating duration 7-148
- Build-only contracts 3-016–3-029
-
Page 1139
- Building control 2-189–2-192
- Building Information Modelling (BIM) 13-067–13-119
- see also BIM
- Business efficacy
- Calculating durations 7-143–7-163
- bricklaying 7-148
- Calculating time-related compensation 10-089
- Cascade diagram 8-048, 8-049
- Cash flow monitoring 9-105–9-110
- Catastrophes
- Causation 14-001–14-264
- acts or omissions of third parties 14-061–14-067
- as-planned versus as-built 14-232–14-241
- bar charts 14-223–14-231
- collapsing technique 14-242–14-248
- completion delayed 14-150–14-154
- completion likely to be delayed 14-142–14-144
- completion likely to be or has been delayed 14-145–14-149
- contemporaneous analysis 14-015–14-018, 14-020
- delay to completion of works 14-107–14-129
- delay to progress of works 14-070–14-081
- developer’s acts or omissions 14-045–14-060
- expenditure of prime cost and provisional sums 14-033–14-044
- factual materials available 14-165–14-172
- failure to perform 14-099–14-106
- inference 14-001-14-008, 14-191–14-252 see also Inference of causation
- instructed changes 14-028–14-032
- instructed variations 14-082–14-087
- matters to be identified 14-009
- occurrences 14-068, 14-069
- other occurrence 14-025–14-069
- primary 14-025–14-069
- proof of 14-130–14-190
- proportionality 14-173–14-190
- retrospective delay analysis 14-019, 14-020
- secondary 14-070–14-081
- smoke and mirrors 14-252–14-264
- subject-matter of proof 14-160–14-164
- suspension of works 14-088–14-098
- terms of contract 14-134–14-159
- tertiary 14-107–14-129
- three-part chain 14-021–14-129
- visualisations 14-249–14-252
- voluntary or implied variations 14-028–14-032
- whatever is fair and reasonable 14-155–14-159
- Cause and effect matrix 14-199–14-207
- CDBs 24-036–24-041
- Change 12-001–12-197
- Change control 13-026–13-041
- clear factual evidence, need for 13-033
- Change management
- definitions 10-049
- effects of change See also Managing effect of change
- acceleration 10-074, 10-085–10-088
- ad hoc changes 10-078
- change order procedure 10-077
- changed resources 10-072
- design changes 10-076
- disruption 10-074
- extensions of time 10-072
- need for instructions 10-075
- sequence of works 10-072
- schedule, and 10-074
- significance of change 10-073
- tenders, and 10-071
- variation 10-072, 10-077
- electronic submittals 10-056, 10-057
- key dates 10-059, 10-060
- management information structure 10-048
- programme 10-050–10-055
- progress records 10-058
- relationships 10-061–10-070
- roles 10-061–10-070
- supplements 10-045–10-070
- Change order procedure 4-109–4-111
- CIOB
- working group 1-011
- CIOB Complex Projects Contract
-
Page 1140
- see also CPC 2013
- Circumstances beyond control 4-042–4-051
- Civil commotion 4-241–4-253
- Claim preparation 22-020–22-023
- Claims consultants 22-027, 22-028
- Classification of change 4-011–4-027
- Collapsed as-built
- Commercial risk allocation
- implied terms, and 2-081
- Compensation see Damages
- Compensation conditional upon notice 5-151–5-165
- Complex projects
- characteristics 3-004
- Complex projects
- risk 2-004
- Computer generated evidence 13-185–13-191
- Computer software 9-007, 9-010
- Computerised database 13-045, 13-046
- Computerised simulation
- Computers
- critical path method, and 7-082
- Conciliation 22-096–22-098
- Concurrency 18-001–18-140
- application of theory 18-007
- concurrent delays to completion 18-066–18-080
- delay to progress, and 18-039–18-065
- distinguishing concurrent and pacing delays to progress 18-024
- distinguishing concurrent and parallel delays 18-018–18-022
- distinguishing concurrent and sequential delays 18-023
- distinguishing delay and financial loss 18-035–18-038
- distinguishing delay to progress from delay to completion 18-015, 18-016
- distinguishing primary, secondary and tertiary causation 18-017
- distinguishing timing of primary cases 18-025–18-028
- entitlement 18-014
- extensions of time, and 18-066–18-102
- inconsistency in treatment of issues 18-012
- legal concepts of relief and compensation 18-029–18-034
- meaning 18-001, 18-002
- pacing, and 18-122–18-140
- parallel causes of delay to completion 18-097–18-102
- parallel delays to progress 18-059–18-065
- parties 18-013
- prolongation, and 18-103–18-121 see also Prolongation
- sequential causes of delay to completion 18-081–18-096
- sequential delays to progress 18-044–18-058
- Consequential changes 12-196, 12-197
- Constructing Excellence 1-006
- Construction industry
- decrease in output 1-001
- Construction management contracts 3-036–3-046
- Construction records 13-001–13-275
- Constructive acceleration 11-093–11-136
- Construction risk 2-125–2-141
- Constructive change 12-158–12-197
- alternative materials 12-188
- avoiding disputes 12-180
- consequential changes 12-196, 12-197
- constructive, meaning 12-162
- essence of claim 12-161
- estoppel, and 12-171
- implied changes, and 12-164, 12-168
- quality 12-181–12-189
- quality or quantity 12-178
-
Page 1141
- reasonable satisfaction 12-182
- treated as variation 12-176
- variations in writing 12-167
- waiver, and 12-171
- when arising 12-175
- Constructive notice 5-030–5-032
- Consumer Insurance (Disclosure and Representation) Act 2012 2-163, 2-164
- Contemporaneous records
- meaning 13-030
- Contingency
- Contingency planning 16-006
-
Contra proferentem rule
- notice as condition precedent, and 5-130
- Contract administrator 1-023
- Contract programme 9-017, 9-018
- Cookham Wood
- Cost and time management
- Cost management 2-014
- Cost monitoring 9-111–9-115
- Costs 22-009–22-023
- Count the squares chart monitoring 9-128–9-135
- Counterclaim 22-140–22-144
- CPC 2013 3-007–3-015
- CPM programming 7-008–7-014
- Critical path 1-028, 1-029
- Critical Path Method 1-029, 7-068–7-084
- DABs 24-036–24-041
- Damage caused by carrying out works 4-255–4-259
- Damages 21-001–21-291
- burden of proof 21-009
- compensation, entitlement to 21-013–21-039
- contractor has actually suffered loss or expense 21-172, 21-173
- direct labour costs 21-042–21-052
- direct loss or expense 21-002, 21-010–21-012
- Eichleay formula 21-185–21-187
- Emden formula 21-189
- exclusion clauses 21-264–21-291
- financing costs 21-119–21-137
- formula adjustments 21-159–21-191
- four-phrase analysis 21-008
- goods and materials 21-074–21-078
- Hadley v Baxendale, rule in 21-003–21-007
- head office costs 21-111–21-116
- Hudson formula 21-188
- insurances 21-117, 21-118
- Lilley Ames Co v United States 21-190
- liquidated see Liquidated damages
- loss of future profits 21-140–21-145
- loss of productivity 21-089–21-097
- loss or expense not recovered elsewhere 21-174
- loss or expense remained unabsorbed 21-175
- management costs 21-068–21-073
- non-productive overtime 21-053–21-057
- plant and equipment 21-079–21-088
- potential heads of claim 21-040–21-158
- preliminaries 21-100–21-110
- profit on costs 21-138, 21-139
- propositions 21-004
- quantifying predictive loss 21-247–21-291
- quantum meruit 21-192–21-223 see also Quantum meruit
- resort to formula approach 21-176–21-184
- staff costs 21-058–21-067
- temporary works 21-098, 21-099
- time-related costs 21-027
- unabsorbed overheads 21-146–21-158
- work-related costs 21-027
- Database records 13-172–13-184
- Databases 13-217–13-235
- DBs 24-001–24-089
- ad hoc 24-026–24-035
- advantages 24-017
- context 24-005–24-016
- costs 24-075–24-081
- enforcement of decisions 24-067–24-072
-
Page 1142
- international developments 24-082–24-089
- national developments 24-082–24-089
- operations 24-053–24-066
- refusal prior to arbitration 24-073–24-074
- rules 24-042–24-047
- standing 24-026–24-035
- use of 24-002–24-004
- Decennial liability
- Defence, statement of 22-137–22-139
- Defined provisional sums 12-101, 12-102
- Delay
- adverse effect 1-033
- advice as to cause of delay 5-039
- analysis, nature of 7-001
- apportionment 20-013–20-031
- build-only contracts 3-022
- catastrophes 4-261
- causation
- “causes” of delay 4-021
- comparative term, as 1-032
- completion 1-002
- concurrent
- completion, to 18-066–18-080
- distinguishing concurrent and pacing delays to progress 18-024
- distinguishing concurrent and parallel delays 18-018–18-022
- distinguishing concurrent and sequential delays 18-023
- distinguishing delay and financial loss 18-035–18-038
- distinguishing delay to progress from delay to completion 18-015, 18-016
- parallel causes of delay to completion 18-097–18-102
- parallel delays to progress 18-059–18-065
- progress, and 18-039–18-065
- SCL Protocol 10-040
- sequential causes of delay to completion 18-081–18-096
- sequential delays to progress 18-044–18-058
- culpable delay 11-090, 11-193, 11-196, 11-201, 11-202, 11-204
- extensions of time
- developer’s time risk event occurring in period of culpable delay to completion date 6-100–6-105
- facts of delay 13-193–13-235
- forecasting delay 10-005-10-013
- foreseeable delay 11-200
- managing effects of delay 10-016
- meanings 1-030, 1-031
- nominated subcontractors and suppliers’ delay 4-196, 4-197
- receiving instructions, in 4-204–4-231
- retrospective analysis 7-077, 14-019, 14-020
- standard clauses of delay 4-028–4-266
- standard form provisions, meaning of delay 2-027
- Design
- meaning 12-070
- Design and build contracts 3-030–3-035
- Design risk 2-095–2-108
- accelerated design programmes 2-102
- approximate bills 2-108
- communication between developer and designer 2-101
- errors 2-095
- fitness for purpose 2-096
- freezing design at scheme design stage 2-104
- key concepts 2-096
- M&E engineering consultants 2-103
- needs of client 2-099
- post-contract design 2-105–2-107
- reappraisal of design 2-106
- reasonable skill and care 2-096
- relevant factors 2-098
- remedial work 2-100
- statistics 2-097
- Detailed plan 7-024
- Developer’s acts or omissions
- Development control 2-193
- Development programme 7-038–7-042
- Diligently
- Dilution of supervision
-
Page 1143
- Disclosure 13-236–13-275
- Discovery 13-226–13-275
- Discrepancies 12-110–12-135
- Dispute boards 24-001–24-089
- see also DBs
- Dispute resolution 22-085–22-098
- see also Conciliation, Mediation
- adjudication 22-106–22-112
- arbitration 22-114–22-122
- causes of dispute 22-085
- choice of method 22-086
- differences 22-088
- expert determination 22-100–22-105
- final and binding 22-113
- informal methods 22-086
- litigation, and 22-121, 12-122
- non-binding 22-089–22-090
- procedures 22-090
- Dispute risk 2-086–2-094
- Disruption
- Divergences 12-110–12-135
- Document management systems 13-226
- Documentary evidence 13-168–13-171
- DRBs 24-036–24-041
- Duress 22-065–22-074
- Early completion
- Early warnings 5-003–5-007
- Earned value monitoring 9-116–9-118
- Economic duress 22-065–22-074
- EDI agreement 13-055–13-057
- Editing standard forms 2-074–2-077
- Egress 4-164–4-170
- Eichleay formula 21-185–21-187
- Electronic data exchange 13-051–13-066
- technologies 13-052
- Electronic documents
- Emden formula 21-189
- Equitable adjustment 1-016
- Errors
- Errors in contract documents 4-081–4-102
- Evidence 13-160–13-192
- computer generated 13-185–13-191
- database records 13-172–13-184
- documentary 13-168–13-171
- facts of delay 13-193–13-235
- manual sorting of 13-204–13-207
- multi-volume collections 13-208, 13-209
- oral 13-161–13-167
- presentation 13-160–13-192
- retrospective assembly 13-196–13-203
- single-volume tagged collections 13-210–13-216
- sorting on databases 13-217–13-235
- strength of records 13-192
- Excepted risks 2-152–2-162
- Exceptionally inclement weather 4-123, 4-127–4-129
- Exclusion clauses
- Expert determination 22-100–22-105
- Expert opinion
- Experts 22-029–22-056
- Experts’ documents
- Extended working hours
- Extensions of time 6-001–6-105
- bar chart 6-064–6-067
- calculating entitlement 10-036
- change management, and 10-072
- coldly logical approach 6-057
- concurrency, and see Concurrency
- conditional upon notice 5-110–5-150
- conduct requiring 11-110, 11-116
- consequences 6-028, 6-029
- constructive change 6-059
- contract administrator, role of 6-014–6-030
- critical delay to the work 6-030
- delay actually occurred 6-036–6-038
- delay to progress 6-002–6-013
- developer’s time risk event occurring in period of culpable delay to completion date 6-100–6-105
-
Page 1144
- forming opinion 6-044–6-068
- holiday period 6-003–6-005
- inoperable power 6-134–6-173
- likely and actual delay to completion date 6-031–6-043
- logical analysis 6-063
- measurement of interim extensions of time 10-018
- negotiating award 6-069–6-074
- no power, where 6-130–6-133
- original planned schedule, and 6-018
- purpose 6-001
- relevant delay 6-042
- restricted working calendars 6-006
- reviewing award 6-088–6-099
- rules of measurement, and 6-060
- standard forms 4-005–4-008
- time risk event 6-032, 6-033
- timing of award 6-075–6-087
- Facts of delay 13-193–13-235
- Failure to pay 4-037–4-041
- Failure to perform
- Familiarisation
- planning, and 7-021
- Financial risk 2-142–2-147
- Financing costs
- Fire
- Fitness for purpose
- Float
- calculation 16-009–16-011
- data 16-009
- definition 16-058–16-060
- elusive concept 16-007
- free 16-012–16-017
- independent 16-018, 16-019
- interfering 16-020, 16-021
- meaning 16-001–16-005
- negative 16-043
- standard form provisions 16-058–16-072
- time contingencies 16-044–16-057
- total 16-022–16-042 see also Total float
- who owns 16-073–16-150
- Flow chart 8-018, 8-019
- Force majeure 4-053–4-080
- Forecasting delay 10-005-10-013
- Forensic
- meaning 15-001
- Forensic programme analysis 15-001–15-175
- analytical methods 15-061–15-163
- as-built schedule 15-047
- as-planned impacted 15-077–15-116
- as-planned updated versus as-planned updated 15-069–15-076
- as-planned versus as-built 15-061–15-068
- collapsed as-built 15-117–15-148
- correcting planned programme 15-019–15-036
- dynamic methods 15-006
- planned programme 15-017
- preparing materials 15-017–15-060
- static methods 15-005
- time impact analysis 15-149–15-163
- updating planned programme with progress 15-037–15-046
- use of 15-004
- watersheds 15-164–15-175
- windows 15-164–15-175
- Formula adjustments
- Fossils 4-264–4-266
- Free float 16-012–16-017
- Fraud 22-075–22-084
- Gantt chart 8-008, 8-009
- Global claim 19-001–19-072
- Goods and materials
-
Page 1145
- Graphs 14-216–14-222
- Greenfield sites
- biddability risk, and 2-116
- Groundworks
- Guaranteed maximum price 3-056–3-059
- Head office costs
- Health and safety 4-254
- Hierarchy of documents 4-081–4-084
- High-rise building projects
- risk 2-005
- Histograms 14-216–14-222
- Holyrood 2-009
- Hong Kong forms
- project planning and programming 2-053
- Hudson formula 21-188
- Human rights
- Identifying cost of project controls 10-090
- Implied instruction for change 12-003
- Implied terms 2-078–2-085
- Inclement weather 4-124–4-126
- Inconsistencies in contract documents 4-081–4-102
- Independent float 16-018, 16-019
- Independent information management 13-120–13-134
- Inference of causation 14-191–14-252
- Inflation 2-147
- Ingress 4-164–4-170
- In-house departments 22-024–22-026
- Injury or damage to property 2-157–2-162
- Inspection 13-236–13-275
- Instructed variation
- Instructed variations and changes 4-103–4-120
- Insurable risk 2-150–2-162
- Interfering float 16-020, 16-021
- Internet
- weather information via 4-131
- Interpretation of contracts
- Itemised bills of quantities
- biddability risk, and 2-122
- Investment decision 2-142
- Latent conditions 4-154
- Learning curve
- Legal risk 2-064–2-085
- court interpretations 2-066
- editing standard forms 2-074–2-077
- implied terms 2-078–2-085 see also Implied terms
- intentions of parties 2-070, 2-071
- interpretation of commercial contracts 2-072, 2-073
- interpretation of standard forms, effect 2-069
- issues 2-064
- ways in which arising 2-065
- where falling 2-067, 2-068
- Line-of-balance chart 8-020–8-026
- Liquidated damages 21-224–21-246
- Litigation 22-119–22-122
- Local authorities
- Logical relationships 7-116–7-125
-
Page 1146
- Loss of future profits
- Loss of morale
- lost productivity, and 17-065
- Loss of productivity
- Loss or expense, recovery of 4-267–4-366
- CIOB Complex Projects Contract 4-325–4-366
- claims procedure 4-300–4-321
- compensable events 4-280–4-299
- compensable risks 4-295, 4-296
- compensation for disruption to progress 4-322–4-324
- conditions contrary to public interest 4-299
- developer’s cost risk events 4-282–4-293
- direct loss and/or expense 4-267
- JCT Major Projects Contract 4-325–4-366
- priced activity schedule 4-279
- standard forms provisions 4-268–4-276
- valuation 4-274–4-278
- variations 4-294
- Lost productivity
- acceleration 17-046–17-052
- accounting for effects of separate events 17-137–17-147
- adverse weather 17-059–17-064
- analysis 17-088–17-162
- burden of proof 17-005, 17-006
- causation 17-007
- conditions causing 17-031–17-034
- difficulty of measurement 17-018
- dilution of supervision 17-075–17-077
- errors 17-053–17-055
- expert opinion 17-160–17-162
- extended working hours 17-066–17-069
- inducing productivity norms versus actual 17-108–17-117
- learning curve 17-078–17-080
- logistics 17-081, 17-082
- loss and expense suffered 17-004–17-008
- loss of morale 17-065
- matters to be proved 17-004
- measured mile 17-124–17-159
- omissions 17-053–17-055
- partial possession 17-056–17-058
- reassignment of manpower 17-070–17-074
- records, and 17-025–17-030
- recovery 17-046–17-052
- ripple 17-083–17-085
- resource-based planning 17-019–17-024
- site restrictions 17-081, 17-082
- staffing 17-035–17-037
- trade stacking 17-086, 17-087
- variations 17-038–17-045
- M & t engineering consultants
- design risks, and 2-103
- Management contracting
- risk, and 2-037
- Management contracting contracts 3-047–3-055
- Management costs
- Managing effect of change 10-071–10-088
- see also Change Management
- disruption 10-074
- first step-programme update 10-080
- frozen design 10-076
- negotiation of variations 10-077
- potential fifth step-acceleration 10-085–10-088
- potential fourth step-event impacting 10-084
- second step-programme review for better information 10-081
- significance 10-073
- third step-recovery 10-082, 10-083
- variation 10-072
- Mandatory laws in international construction contracts 25-001–25-026
- Manifest error
- biddability risk, and 2-121
- Master programme 7-028–7-037
- Measured mile 17-124–17-159
- Mediation 22-091–22-095
-
Page 1147
- Milestone programme 8-029–8-032
- Milestones 7-098–7-109
- Mismanagement of time
- Misrepresentation 22-075–22-084
- Mitigation 11-001–11-020
- Modelling 9-008
- Monitoring
- Natural justice
- dispute risks, and 2-094
- Negative float 16-043
- Negligence
- Network diagrams 8-033–8-035
- Nominated subcontractors and suppliers 4-189–4-203
- Non-productive overtime
- Notice as condition precedent 5-110–5-165
- Notices 5-008–5-109
- Occupational programme 7-055–7-057
- Omissions 12-136–12-153
- Oral evidence 13-161–13-167
- Outline plan 7-022
- Pacing 18-122–18-140
- Partial possession
- Partnering 3-060–3-063
- Penalties 21-232–21-241, –21-260
- PIX Protocol 13-061–13-066
- Planning
- Plant and equipment
- Political risk 2-148, 2-149
- Poor project programming 1-009
- Poor record keeping 1-009
- Postponement 4-171, 4-172
- Precedence diagram 8-043–8-047
- Preliminaries
- Presentation of programmes 8-001–8-091
- compliance with scheduling specifications 8-006
- Prevention principle
- Private finance initiative 3-064–3-072
- Private international law 25-006–25-009
- Private nuisance 2-183, 2-184
- Privileged communications
- Probability estimates
- Procurement arrangements 3-056–3-072
- Productivity see also Lost productivity
- Profit on costs
- Programme 1-025
- activity coding 7-232
-
Page 1148
- contract document, as 7-222–7-228
- core principles 7-234
- method of compilation 7-229
- presentation 8-001–8-091
- pricing requirements 7-243–7-247
- specifying requirements 7-229–7-242
- standard form requirements 7-179–7-247 see also Standard form requirements for programmes
- subject-matter 7-241
- varieties 7-026–7-065
- Programme preparation 7-068–7-163
- Programme revision 9-061–9-068
- Programme updating 9-069–9-088
- Programming
- Progress monitoring 9-089–9-149
- Progress records 13-015–13-025
- Progress reporting 9-150–9-175
- Project control 10-001–10-094
- Project planning and programming
- Project planning model statements 7-164–7-178
- Project procurement 3-001–3-072
- Project time manager 3-011
- Projects
- meaning 3-004
- Prolongation 18-103–18-121
- Proportionality
- PSSC 3-014
- Public private partnership 3-064–3-072
- Quality control 4-232–4-240
- Quantifying predictive loss 21-247–21-291
- likely outgoings 21-262
- Quantum meruit 21-192–21-223
- Rate of progress
- meaning 11-080
- Reasonable skill and care
- risk, and 2-049
- Reassignment of manpower
- Record keeping 13-003–13-014
- Record retrieval 13-042–13-050
- Records
- Recovery
- Regularly
- Re-measurement
- build-only contract 3-028
- Re-measurement contracts
- risk 2-036
- Reporting
- Request for further information 22-151–22-154
- Retrospective delay analysis 7-077
- Residential occupiers
- adjudication in UK 23-0455–23-047
- Resource-based planning
- Resource monitoring 9-097–9-104
- Revision
- RIBA Plan of Work 2013 3-015
- Ripple
- Risk 2-001–2-193
- acts of prevention 2-046
- advice on 2-014
- allocation 2-103–2-015, 2-038–2-164
- bespoke form, and 2-044
- biddability see Biddability risk
- buildablity see Buildability risk
- categorisation 2-017
- commercial negotiation 2-041
- complex projects 2-004
- computerised simulation 2-061–2-063
- conflicting interests of parties 2-040
- construction see Construction risk
- design see Design risk
- design and build contracts 3-034, 3-035
- dispute see Dispute risk
- distribution 2-042
- financial see Financial risk
- fitness for purpose, and 2-049, 2-050
- high-rise building projects 2-005
- identifying 2-016
- ill-considered transference 2-025
- influence of variables 2-012, 2-013
- insurable 2-150–2-162
- JCT forms 2-019, 2-020
- judicial interpretations of common law and statute 2-047
- legal see Legal risk
- management 2-015, 2-016
- management contracting 2-037
- managing risk of change 2-031
- obligations of professional and tradesman 2-048
- political see Political risk
- probability estimates 2-059, 2-060
- project planning and programming 2-051–2-062
- reasonable skill and care 2-049
- registers 2-033
- re-measurement contracts 2-036
- responsibilities of parties 2-038
- sources 2-010, 2-011
- standard form provisions 2-018–2-037
- statistics 2-001–2-003
- theories of apportionment 2-043
- Risk allocation
- tort, and 2-169
- Schedule 1-025
- Schedule logic 7-078
- Scheduling
- see also “Critical path method”
- approval and presentation
- activity-based CPM schedule 8-002, 8-034
- complex projects 8-002
- computer programmes 8-001
- contract requirements 8-005
- contract specification 8-003, 8-004
- CPM-based algorithms 8-002
- electronic information 8-004
- engineering contracts 8-004
- generally, 8-001
- line of balance charts 8-020
- management information 8-004
- methods, 8-002
- milestone charts 8-029–8-032
- network diagrams, 8-033, 8-034
- network planning techniques 8-035
- precedence diagrams 8-043
- resource loading 8-002
- software 8-002
- specifications 8-006
- standard form contracts 8-004
- time change diagrams 8-027, 8-028
-
Page 1150
- delay analysis 7-002
- development process 7-025
- excusable delay 7-008
- late 8-005
- planning
- programming 7-025
- progress monitoring 9-004, 9-086
- reporting 9-005
- updating 9-069
-
SCL Protocol
1-004, 1-005, 10-014–10-044
- calculating entitlement to extension of time 10-036
- complex scheduling and record-keeping equipment 10-042
- concurrent causes of delay 10-040
- contemporaneous project control 10-019
- critical path network 10-023
- float 10-037
- identification of activities 10-024
- information 10-025
- managing effects of delay 10-016
- measurement of interim extensions of time 10-018
- nature of 10-015
- objection to electronic access to schedule 10-031
- public health guide, as 10-043
- record-keeping 10-026, 10-027
- retrospective analysis 10-017
- schedule and records 10-020
- update of contractor’s schedule 10-028–10-030
- Scott schedules 14-208–14-215
- Second notice 5-081–5-089
- Sectional completion 7-098–7-109
- Sequencing problems 2-111
- Service of notice 5-097–5-109
- Settlement 22-057–22-064
- Simple projects
- characteristics 3-004
- Site restrictions
- Smoke and mirrors 14-253–14-264
- Soft-spots 4-145
- Special circumstances 4-052
- Specified perils 2-150, 2-151
- Staff costs
- Staffing
- Standard clauses of delay 4-028–4-266
- Standard form provisions
- Standard form provisions for time and cost 4-001–4-366
- Standard form requirements for programmes 7-179–7-247
- Standard forms
- Statements of case 22-123–22-129
- Statement of claim 22-001–22-008, 22-130–22-136
- Statutory compensation schemes 2-181, 2-182
- Statutory duties 2-165–2-193
- Statutory undertaker 4-174
- Strategic plan 7-023
- Strikes 4-241–40253
-
Page 1151
- meaning 13-228
- Subcontractors
- Subcontractor’s programmes 7-059–7-067
- Suspension of works
- Target costs 3-056–3-059
- Target CPM programme monitoring 9-091–9-096
- Target programme 7-028–7-037
- Temporary works
- Tender programme 7-028–7-037, 7-043–7-046
- Terminology 1-019–1-034
- Terms of contract
- Terrorism 4-248, 4-251
- The contractor 1-021
- The developer 1-022
- The works 1-024
- Time and cost
- Time at large 6-106–6-129
- Time-bar clauses
- Time chainage diagram 8-027, 8-028
- Time contingencies 16-044–16-057
- Time impact analysis 15-149–15-163
- Time management
- Tort 2-165–2-193
- Total float 16-022–16-042
- ad hoc creation 16-088–16-096
- belongs to contractor 16-123–16-133
- belongs to developer 16-120–16-122
- belongs to first to get to it 16-134–16-150
- contingency, interpretation as 16-097–16-119
- absence of completion constraint on planned work 16-100–16-106
- applied completion constraint upon placed work 16-103–16-106
- applied fixed lag between unconstrained milestones 16-110–16-112
- contract duration bar 16-115–16-119
- non-driving link between applied constraints 16-107–16-109
- time contingency activity 16-113, 16-114
- Total loss claim 19-001–19-072
- Total time claim 19-001–19-072
- Trade stacking
- Trade usage
- implied terms, and 2-083
- Unabsorbed overheads
- Undefined provisional sums 12-101
- Unforeseeable physical conditions 4-144–4-163
- Unjust enrichment 21-194
- Updating
- US government procurement contracts 1-015
- Utilities
- Value engineering 12-154–12-157
- Variation 12-001–12-197
- see also Change
- ambiguities 12-110–12-135
- definition 12-032–12-036, 12-038, 12-043, 12-048, 12-049, 12-056, 12-059
- discrepancies 12-110–12-135
- divergences 12-110–12-135
- drawings 12-019
- extra work 12-026, 12-027
- instruction, definition 12-055
- legitimate power to instruct 12-015
- lost productivity, and 17-028–17-045
- necessary work 12-023, 12-024
- omissions 12-136–12-153
- post-contract design 12-021
- price 12-017
-
Page 1152
- standard form provisions 12-030–12-157
- VATFP 17-012, 17-013
- Visual aids 9-161–9-175
- activity lists 9-167
- assessment tables 9-168
- bar charts 9-169–9-171
- cascade diagrams 9-167
- computer printouts 9-167
- computer-generated visualisations 13-249
- descriptive visualisations 9-162, 13-188, 14-250
- electronic spreadsheets, 9-175
- evidential visualisations 9-165, 13-191
- graphs 9-172–9-174
- histograms 9-169
- illustrative visualisations 9-164, 13-190, 14-252
- introductory visualisations 9-163, 13-189, 14-251
- probative value 9-161
- progress reports 9-150–9-160
- Visualisations
- Voluntary change 12-002
- War 4-249–4-252
- Watersheds
- Weather 4-121–4-143
- actual effect of conditions 4-139
- average 4-132–4-135
- causation 4-133
- construction risk, and 2-140, 2-141
- exceptionally inclement 4-123, 4-127–4-129
- force majeure, and 4-142
- inclement 4-124–4-126
- information via internet 4-131
- measurement 4-136, 4-137
- the force of nature, and 4-141
- variable conditions 4-121
- Windows
- Work content 7-110–7-115
- Work content monitoring 9-144–9-149
- Working programme 7-047–7-054