IN RE BLYTH SHIPBUILDING & DRY DOCKS COMPANY, LTD.
(1925) 23 Ll L Rep 78
CHANCERY DIVISION.
Before Mr. Justice Romer.
Company-Receiver-Contract to build ship -Ship partly built-Power of receiver appointed by debenture holder to suspend work under contract and to dispose of partly built ship and materials.