REDERI AKTIEBOLAGET BYLGIA v. ANGLO-SOVIET SHIPPING COMPANY, LTD.
(1932) 44 Ll L Rep 344
KING'S BENCH DIVISION.
Before Mr. Justice Roche.
Charter-party- Insurance of vessel- Extra cost owing to delay - "Charterers undertake to load steamer and clear the cargo and present the master with bills of lading for signature so early as to enable the pilot to take the steamer out not later than Oct. 31, failing which charterers are to pay the actual amount paid by owners to underwriters for extra insurance on present policies, excepting in cases of delay attributable to owners or steamer."- Delays on voyage to loading port due (1) to defects in steam pipe affecting working of windlass; (2) to defects in steering gear; (3) to collision with another vessel; (4) to bad weather