LAMPSON BROS., LTD. v. LILLEY & CO.
(1936) 54 Ll.L.Rep. 331
KING'S BENCH DIVISION.
Before Mr. Justice MacKinnon.
Stevedores-Discharge of defendants' ship loaded with cargo of sawn timber from Archangel-Claim by plaintiff stevedores for damages consequent upon time alleged to have been lost in discharge-Provision in contract for standing by for rain - Plaintiffs' contention that delay occurred owing to incorrect stowage plan and that there should be implied in the contract a term that cargo should be accurately stowed-Evidence of delay owing to failure of steam.