DAWNAYS LTD. v. F. G. MINTER LTD. AND TROLLOPE & COLLS LTD.
[1971] 2 Lloyd's Rep. 192
COURT OF APPEAL
Before Lord Denning, M.R., Lord Justice Edmund Davies and Lord Justice Stamp
Building contract - Sub-contract - R.I.B.A. forms - Interim certificate of money due to sub-contractors - Delay by sub-contractors causing work to be held up on main contract - Alleged loss to main contractors - Whether main contractors had right to withhold payment of money due to sub-contractors.