MILLER CONSTRUCTION LTD v JAMES MOORE EARTHMOVING
[2001] BLR 10
QUEEN’S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT
Before His Honour Judge Richard Seymour QC
Arbitration - Misconduct - Removal of arbitrator - Opportunity to be heard - Pleaded case - No prejudice caused by misconduct - Decisions on issues deferred - FCEC Subcontract - Clause 10(2) - Main Contract benefits - Variations.