Law of Construction Disputes, The
Page 521
Appendix 7
Dispute Board Provisions Under the FIDIC Silver Book
FIDIC (Silver Book)
Conditions of Contract for EPC Turnkey Projects
Sub-Clause 20 Claims, Dispute and Arbitration
20.1 Contractor’s Claims
If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Employer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.