Chern on Dispute Boards
Page 687
APPENDIX 2
FIDIC Conditions of Contract for Plant & Design-Build, First Edition 1999 (Yellow Book)
FIDIC Conditions of Contract for Plant & Design-Build, First Edition 1999 (Yellow Book)
1Sub-Clause 20—Claims, Disputes and Arbitration
20.1 Contractor’s Claims
If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Engineer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.