Litigation Letter
Court of Appeal upholds schedule for interim payments
Balfour Beatty Regional Construction Ltd v Grove Developments Ltd [2016] EWCA Civ 990, 13 October 2016
Balfour Beatty was engaged by Grove to design and construct a hotel and serviced apartment at Greenwich Peninsular under the
JCT standard form Design and Build Contract 2011. The parties agreed that Grove would make interim payments in accordance
with a schedule, which provided for interim payments from September 2013 to July 2015.