Law of Construction Disputes, The
Page 663
Index
Index
- Abatement
- ACA forms of contract 34
- Accord and satisfaction 199–200
- ACE forms of contract 34, 81, 109
- Act of God 138, 144, 147, 321
-
Adjudication
344, 357–358
- development of non-statutory 24–33
- Dispute Adjudication Boards see under Dispute Boards
- HGCRA 1996 344, 358–359, 378, 387
- adjudicator 359, 365
- challenging decision 367
- costs 367, 370–371
- dispute 360–362
- dispute under construction contract 363
- enforcement 367–368
- mandatory provisions 358
- mistake: correcting decision 366–367, 371
- NEC3 172
- oral and partly written contracts 363–365, 370
- process 365–368
- reasons for decision 366
- referral notice 365–367
- restrictions 358
- serial decisions 407
- time limits 359, 364, 365, 366
- JCT: changes made in SBC05 168
- NEC3 172
- Scheme for Construction Contracts 168, 358, 359–360, 368
- serial decisions
- Sharia – Islamic law 13
- stare decisis 3
- Affirmation
-
Agency
- subcontractors 139
-
Amicable settlement
- after notice of dissatisfaction 419
- Anticipatory repudiation 194–195
- Applicable law 1
-
Arbitration
347
- agreement 347–348, 387–395
- list of contents 395
- amiable compositeur or ex aequo et bono 350
- Arbitration Act 1996 347
- arbitrator 348–349
- award 349–350, 403
- confidentiality 402–403
- disclosure 395–397
- Dispute Board Decisions 17, 418, 419
- document only 350
- enforcement 13–14
- England: seventeenth century 18–19
- high-low 344, 350
- litigation vs mediation vs 345–346
- mediation 345, 350
- Sharia – Islamic law 10–11, 12, 13–16
-
Page 664
- third parties: 1999 Act 289
- agreement 347–348, 387–395
- Capacity 44
- Causation 236–241, 269–271, 333
-
Certification
203–217
- errors 205–206
- fairness 214–215, 217
- FIDIC Red Book: interim payment certificates 204
- ICE: Measurement Version 169–170
- impartiality of certifier 206–208, 214, 215–216, 217
- interim certificates 206
- liability of certifier
- natural justice 206, 214, 215, 217
- repudiatory breach 189
- requirements, certificate 205
- variations: final certificates 231
- Civil law 6–9, 13, 256
- Claims 235–236
- Collateral warranties 167, 209, 210, 283–289
- Common law 1–6
- Conciliation 345
- Condition precedent
- Conditions
- Confidentiality
- Consideration 44–47
-
Construction contract
- agreement to agree 58
- battle of the forms 51–54
- capacity 44
- conditions 58–59
- consideration 44–47
- defining 41–42
- estimate for work 55–56
- express terms 59, 79, 80, 81, 108, 117, 185, 208, 288
- fairness and fair dealing 56–57, 59
- formation 41–50
- implied agreements 44
- implied terms 58, 59, 99, 108, 407
- innominate terms 59
- intent to be legally bound 47–48
- invitation to treat 42–43
- letters of intent 50
- offer and acceptance 42–44, 52, 54
- oral 49–50, 108
- privity of contract 48–49, 137, 283, 285
- severability clauses 58
- Subject to Contract 52
- tenders 54–57
- uncertainty 58
- unilateral 43–44
- bilateral contract vs 57
- warranties 58
- Construction operations
- Construction tenders 54–57
-
Page 665
- Contribution
- Cost reimbursement or cost plus fee contract 39
- Costs
-
Damages
- civil law countries 256
- contract vs tort 249–254
- defective work 189, 235
- diminution in value 246–247, 271–279
- encroachment 323
- extension of time 265
- FIDIC Forms of Contract 184–185
- instead of rescission 197
- licence to enter site 113, 114, 115, 116
- in lieu of specific performance 255
- liquidated 159, 235, 256–263, 329–334, 336–337, 341
- measure of 235
- misrepresentation 60, 61, 62–63, 123
- negligent misstatement 64
- nuisance 318
- punitive 60, 235
- reasonable cost of remedial works 244–247
- site possession: employer responsibility 126
- tort vs contract 249–254
- trespass 323
- Deceit 63
- Defective Premises Act 1972
- Defences 141
- Delay
-
Design professionals
75–110
- architect/engineer’s duty: tort vs contract 77–78
- concurrent negligence and contract duty 83–88
- delegation of design responsibilities 109–110
- duty to others 100
- fitness for purpose liability 76–77, 78–80, 81–83, 108, 156, 163, 164, 173–174, 180
- knowledge of others 106–107
- latent defects, subsequent occupiers and personal injury 102–103
- matters other than design 107
- NEC3 173–174
- new, novel and strict design standards 89, 107–108
- others, liability for design of 109–110
- physical damage/personal injury 100, 102–103
- purely economic losses 77–78, 83–87, 95–96, 97, 100–102, 105–106
- reasonable skill and care 79, 80–83, 108, 156, 164, 173–174
-
Page 666
- subsequent occupiers, latent defects and personal injury 102–103
- Design-build form contracts 156–175
- Development banks
- Diminution in value
- Disclosure
- Dispute
-
Dispute Boards
17, 372–385
- Adjudication Boards 372, 373, 375–376, 377
- advent in England of 26–27
- advisory opinions 382
- appointment 379–380
- arbitration 17, 418, 419
- available at short notice 382
- costs 383
- enforcement of DAB decisions in interim period before arbitral award 419–434
- growth of 378–379
- history of 376–377
- informal operations 382
- international aspects 385
- interpretation of contract 382
- membership 379–380
- nature of 372–374
- overview 379
- procedures 382–384
- reasons for success 383–385
- Review Boards 372, 373–375, 377
- routine operations 381–382
- Sharia – Islamic law 10, 13, 14–15, 16, 17
- site visits, regular 380–381, 385
- unique 374
-
Dispute resolution
343–385
- adjudication see separate entry
- arbitration see separate entry
- conciliation see separate entry
- conventional model 343
- Disputes Boards see separate entry
- engineer as quasi-arbitrator 21–24
- engineer/arbitrator as judge 19–21
- historical development of 17–19
- JCT: changes made in SBC05 168
- mediation see separate entry
- NEC3 172
- NEC4 174
- overview of forms of 343–345
- Sharia – Islamic law 10–13
-
Disruption
- claims: delay vs 263
- Due diligence 263
- E-disclosure
- Economic duress 47, 199
- Economic loss
- Election
- Encroachment 323
- Engineer as quasi-arbitrator 21–24
- Engineer/arbitrator as judge 19–21
- Estoppel 46
- Executive Tribunal 345
- Expert determination 344–345
- Extension of time (EOT) clauses 159
-
Page 667
-
FIDIC Forms of Contract
34, 175–185, 358
- access to and possession of site 117
- applicable law 1
- certification 204, 214
- common issues between forms
- damages: claims by
- Dispute Boards 376–378, 379, 382–383, 418
- extension of time for completion 265
- force majeure 141–142, 143, 144, 146, 181
- Gold Book 34, 175, 177, 185, 430
- Green Book 156, 175
- proper form
- Red Book 34, 36, 146, 155, 175–176, 180, 184, 377, 420–430
- contractor incentives 178
- engineer 177, 178
- EOT clause 159
- fitness for purpose 157
- ground conditions 119–120
- impossibility 181
- interim payment certificates 204
- risk allocation 177
- termination 181, 191–192
- text 475–485, 487–497
- time-bar 334, 335, 337, 342
- unforeseen conditions 183
- variations 178, 179, 217–218
- Silver Book 34, 175–176, 181, 183, 184, 377
- time limits 418, 419
- Yellow Book 34, 156, 175–176, 181, 184, 377
- Final Account Statements 232–234
- Fixed price contract 38
- Float 267–268
-
Force majeure
141
–
149
- Acts of God and 144
- burden of proof 144
- commencement 147
- duration of condition 148#
- effect of 149
- FIDIC Forms of Contract 141–142, 143, 144, 146, 181
- frustration and 144–145
- mitigation of losses 144, 148
- necessary requirements for 147
- notice of event 148–149
- purpose of clauses 145–146
- termination of contract 143–144
- typical usage 146–147
- Formation of contract 41–50
- France
- Frustration 141, 144–145, 149–153
- Germany
- Glossary of construction terms 435–450
- Good faith 22, 30, 31, 59, 185, 355, 426
- Government forms of contract 34
- Guaranteed maximum price contract 38
- Hanafi Islamic Sharia 10, 11–13
- Hanbali Islamic Sharia 11–13, 14
- High-low arbitration 344, 350
- Housing Grants, Construction and Regeneration Act 1996
- Human rights
- ICE conditions of contract 34, 155, 156, 168–170
- Implied agreements 44
- Impracticability or impossibility of performance 70–71, 145–146
- Injunctions
- Innominate terms 59
- Insolvency
- Intent to be legally bound 47–48
- Interest
- International Chamber of Commerce (ICC) 17, 374, 378, 387
- Invitation to treat 42–43
- Islamic law see Sharia – Islamic law
- Issue estoppel 406–407
- JCT forms of contract 34, 155, 156, 160–168
- Joint ventures 374
- Judicial appraisal 344
- Jurisprudence constante 5 – 6
- Latent Damage Act 1986
- Latent defects, subsequent occupiers and personal injury 102–103
- Letters of intent 50
- Licence to enter site
- Limitations Act 1980
- Liquidated damages 159, 235, 256–263, 329–334, 336–337, 341
- Litigation
-
Loan agreements
- Disputes Boards 380
- Maliki Islamic Sharia 11–13
- Mediation 345
- Methods of construction contracting 35–36
- Misrepresentation 59–65
- Mistake 65
- Natural justice 113–114
- NEC 170, 176
- Negligence 291–316
- Negligent misrepresentation 64
- Negligent misstatement 64, 209–210
- Nemo sua judex in sua causa 21
- Net contribution clauses 283, 285
- Neutral Fact-Finder 345
- Non-contract liability see Tort
- Notice of dissatisfaction
- Nuisance 316–319
- Pacta sunt servanda 21 , 41 – 42
- Payment formats
- Payment(s)
-
Personal data
- protection 398
- Personal injury, latent defects and subsequent occupiers 102–103
- Precedent 2–6
-
Prevention principle
184–185, 271, 325, 327, 331, 337, 340–342
- meaning of 184
-
Privity of contract
48–49, 283, 285
- subcontractors 137
-
Professional indemnity insurance
- reasonable skill and care 79
- Promissory estoppel 200–202
- Ratio decidendi 5
-
Rectification
- mistake 68
- Release
- Remeasurement type of contract 38–39
- Repudiation
- Rescission 197
- RIBA Architect’s Appointment 81, 109
-
Rylands v Fletcher
319
–
322
- defences 321
- Sale of Goods Act 1979
- Scheme for Construction Contracts (England and Wales) Regulations 1998
- Set-off
- Severability clauses 58
- Shafi Islamic Sharia 10–13
- Sharia – Islamic law 9–17
- Site 111
- Specific performance 45, 73, 115, 255–256, 287
- Standard construction contracts
- Standard form contracts 33–34, 155–156
- Stare decisis 2 – 6 , 9
- Strict liability 80
- Subcontractor 127–139
- Subject to Contract 52
- Supply of Goods and Services Act 1982
- Target cost contract 39
- Tenders 54–57
- Termination of contract
- Time at large 159, 325–334, 336, 337
- Time of the essence 72, 151, 190, 325–326, 328
- Time-barred claims 334–342
-
Page 672
- Torts (Interference with Goods) Act 1977
- Traditional lump sum or fixed price contract 38
- Trespass 322–323
- Unconscionability 67, 234, 255, 257, 258–259, 262, 333
- Unfair Contract Terms Act 1977
- Unilateral contracts 43–44, 57
- Unjust enrichment 44