JCT Contract Administration
Page 59
3
Interim payments
Introduction
It is traditional to make payments on account for building work, although for normal lump sum contracts this is not legally necessary. In the absence of express terms, payment would become due when the building was complete. However, three factors have led to the introduction of such terms: