Adjudication in Construction Law
Page 621
Index
Index
-
Abridgment of time
- in enforcement proceedings 6.6
-
Abuse of process
- beginning adjudication 2.15.2
- Adjudication
- Adjudication notice. See Notice of intention to refer
-
Adjudication scheme for professional negligence claims
- generally 9.8
-
Adjudicator
- appointment. See Appointment of adjudicator
- bias. See Bias
- communications with the parties 4.9
- consideration of evidence and law 4.12
- consideration of evidence under investigative jurisdiction 4.12.1
- constraints upon adjudicators 4.11.11
- corporate body 3.1
- declaration of interest by 3.7
- declining to consider evidence adjudicator 4.12.2
- declining to consider late material 4.12.6
- experience as an advocate 4.11.7
- failure to inform other party of communications with party 4.9
- failure to carry out site inspection 4.12.8
- fees and expenses. See Fees and expenses
- interest as defence to enforcement 6.16
- jurisdiction in absence of certificate 10.10.2
- jurisdiction in relation to conditional payment 10.10
- not obliged to accept submission of one party or the other 4.11.4
- obligation to resign 4.5.1
- obtaining legal advice 4.11.13
- own knowledge and experience 4.11.6
- participation in experts’ discussions 4.10.4
- participation in ‘without prejudice’ negotiations 4.10.1
- person, must be 3.1
- use of alternative approach 4.11.3
- who may act as 3.1
- Administration
-
Administrative receivership
- effect on enforcement 6.12.5
-
After the event (ATE) insurance
- in relation to enforcement proceedings 6.35.4
-
Agreed contractual relationship
- generally 4.13.5
-
Agreements made under statutory agreements
- meaning 1.13.1
-
Agreement to widen jurisdiction
- effect of 6.30.1
-
Alberta
- Adjudication in 7.6.4
-
Ambit of Dispute
- generally 4.13
-
Ambush
- by adjudication 2.15.5
-
Amec case
- dispute 2.4.1
-
Ancillary matters
- generally 4.13.4
-
Any ground open allowed for defence
- generally 4.13.3
-
Appointment of adjudicator
- contract of appointment 3.3
- contract with neither party 3.3.3
- contracts between parties and adjudicators and nominating bodies 3.2.4
- contractual relationship between adjudicator and parties 3.3.1
- effect of jurisdictional challenge 3.3.5
-
Page 622
- invalid 3.2.5
- joint and several liability 3.3.4
- non-compliance with statutory requirements 3.2.2
- statutory requirements 3.2.1
- unilateral appointments 3.3.2
-
Approbation and reprobation
- generally 6.31
-
Arbitration
- compared with adjudication 2.13
-
Architectural, design, or surveying work
- meaning 1.10
- Arising under the contract
-
Assignment
- as potential defence to enforcement 6.28
- At any time
-
Australia
- Overview 7.2
-
Australian Capital Territory
- adjudication in 7.2.19
-
Background to Part II of the 1996 Act
- generally 1.2
-
Bias
- adjudicator's communications with parties 4.9
- adjudicator's participation in ‘without prejudice’ negotiations 4.10.1
- circumstances giving rise to 4.7.3
- impartiality in conduct of adjudication 4.8
- in summary 4.7
- receipt of evidence during negotiations 4.10.2
- risk of bias and consequences 4.10.3
- adjudicator's participation in experts’ discussions 4.10.4
- submission of ‘without prejudice’ material to adjudicator 4.10.5
- ‘without prejudice’ negotiations and communications 4.10
-
Bouygues
case
- right question 11.2
-
Bresco v Lonsdale
- effect on one dispute rule 11.3.9
-
British Columbia
- adjudication in 7.6.5
-
Burden of proof in court proceedings
- effect of adjudicator's decision on 6.39
- Canada
-
Carrying out or arranging for the carrying out of construction operations
- generally 1.7
-
Centre for Effective Dispute Resolution (CEDR)
- adjudication rules 9.7.3
- Certificate
-
Charging orders
- in enforcement proceedings 6.36.2
- Claim
-
Collateral warranty
- whether construction contract 1.7.6
-
Commercial advantage and lever
- in relation to adjudication 2.15.3
- Communication of Decision
- Company voluntary arrangement
-
Compromises
- generally 2.13.3
-
Concurrent adjudications
- generally 2.12.4
-
Concurrent court proceedings
- generally 6.4.9
-
Conditional fee agreements (‘CFAs')
- in relation to enforcement proceedings 6.35.4
-
Page 623
-
Construction contracts.
See also
Construction operations
- agreements made under statutory agreements 1.13.1
- at common law and under statute 1.5
- categories of regulated by statute 1.6
- contract to conduct negotiations 1.7.7
- contracts and provisions not in writing 1.12
- development agreements 1.13.4
- excluded construction contracts and disapplication of Act 1.13
- finance agreements 1.13.3
- PFI agreements 1.13.2
- residential occupiers 1.11.2
- unregulated contracts 1.11.1
-
Construction Industry Council (CIC)
- adjudication rules 9.7.4
-
Construction operations
- architectural, design, or surveying work, providing advice in relation to construction operations 1.10
- competing constructions as to extent of exemption 1.8.3
- different operations to a building or structure 1.7.2
- example of a structure 1.7.3
- examples of ‘narrow construction’ 1.8.4
- exempted construction operations 1.8
- exempted construction operations relating to plant 1.9
- food and drink 1.8.6
- future work 1.8.7
- generally 1.7.1
- manufacture or delivery to site and installation 1.8.8
- part of the land 1.7.4
- power generation 1.8.5
- test for exemption 1.8.1
-
Construction Supply Chain Payment Charter
- generally 8.12
-
Consumer Code for Home Builders Adjudication Scheme
- adjudication 9.9
-
Consumer contracts
- unfair terms in 1.17
-
Contemporanea expositio est optima et fortissima in lege
- application to s 108 of Housing Grants, Construction and Regeneration Act 1996 11.4.6
-
Contractual adjudication
- Adjudication scheme for professional negligence claims 9.8
- American Institute of Architects (AIA) General Conditions 9.12
- Centre for Effective Dispute Resolution (CEDR) 9.7.3
- Construction Industry Council (CIC) 9.7.4
- Consumer Code for Home Builders Adjudication Scheme 9.9
- Dispute Adjudication Boards 9.10
- FIDIC Dispute Avoidance/Adjudication Boards 9.11
- GC works contracts 9.5
- ICC (ICE) adjudication provisions 9.4
- IChemE adjudication rules 9.6
- in Hong Kong 9.13
- in South Africa 9.14
- Institutional procedural rules 9.7
- in the United States 9.12
- introduction 9.1
- JCT adjudication provisions 9.2
- NEC 4 contracts 9.4
- Technology and Construction Bar Association (TECBAR) 9.7.1
- Technology and Construction Solicitors’ Association (TECSA) 9.7.2
- Correction of errors
- Costs in adjudication
- Costs on enforcement
-
Cross claims
- generally 4.13.3
-
Page 624
- a decision is a ‘decision’ 6.2.3
- binding if adjudication agreement not terminated? 5.3.1
- effect of 6.1
- effect of challenge to validity of 6.2
- formalities 5.5.1
- form of 5.5
- means of communication 5.2.2
- no lien on 5.6.5
- no stay for arbitration 6.2.4
- outside time limit 5.4
- relevance of planning cases 5.5.6
- primary objective of decision within time limit 5.4.1
- principle 5.2.1
- reasons absent or unintelligible 5.5.4
- reasons not required 5.5.2
- reasons to make clear all essential issues decided 5.5.3
- time for payment need not be specified 5.5.7
- time limit for 5.1
- time limit mandatory? 5.3.2
- tolerance of delay for a day or two 5.4.2
- Declaration of interest
-
Declining to consider evidence
- adjudicator 4.12.2
-
Declining to consider late material
- adjudicator 4.12.6
- Defence
-
Deferment of adjudication
- non-compliance with statutory requirements 1.16.1
-
Development agreements
- generally 1.13.4
-
Discussions between parties
- effect on existence of dispute 2.7
-
Dispute
- agreed contractual relationship 4.13.5
- ambit of 4.13
- ancillary matters 4.13.4
- any ground open allowed for defence 4.13.2
- arising under the contract 2.13
- concurrent adjudications 2.12.4
- cross claims 4.13.3
- defence not addressed by the parties 4.13.8
- due date for payment, significance of 2.11
- discussions between parties 2.7
- effect of Statutory Scheme 2.12.2
- meaning of ‘a dispute’ 2.12.1
- more than one dispute 4.3
- one dispute and only one dispute 11.3.1
- origin of one dispute rule 11.3.2
- prevarication and procrastination 2.8
- rejection of a defence not a jurisdictional decision 4.13.6
- role of notice of adjudication 4.13.1
- same or substantially the same as one previously referred 4.5
- silence 2.9
- sustainability of one dispute rule 11.3.8
- Dispute Adjudication Boards
-
East Coast Model
- for adjudication in Australia 7.2.3
-
Enforcement
- abridgement of time 6.6
- approbation and reprobation 6.32
- costs 6.36
- defences to 6.9–23
- effect of challenge to decision 6.2
- effect of decision 6.1
- Europe 6.41
- ineffective defences to 6.24–6
- interest 6.34
- judgment in default 6.7
- methods of 6.3
- of judgment 6.37
- potential defences 6.27–9
- practice and procedure 6.4
- service out of the jurisdiction 6.5
- set-off 6.30
- severability of decision 6.33
- stay of execution 6.35
- summary judgment 6.8
- waiver, agreement and reservation 6.31
-
England and Wales and Scotland
- application of statutory provisions 1.3.1
- Errors
- Evidence
-
Page 625
-
Exempted construction operations
- architectural, design, or surveying work, providing advice in relation to construction operations 1.10
- competing constructions as to extent of exemption 1.8.3
- different operations to a building or structure 1.7.2
- example of a structure 1.7.3
- examples of ‘narrow construction’ 1.8.4
- exempted construction operations 1.8
- exempted construction operations relating to plant 1.9
- food and drink 1.8.6
- generally 1.8
- need for reform? 1.8.2
- test for exemption 1.8.1
- Extensions of time and damages for delay
- Fees and expenses
-
FIDIC
- Dispute Avoidance/Adjudication Boards 9.11
-
Finance agreements
- excluded construction contracts 1.13.3
-
Food and drink
- exempted construction operations 1.8.6
-
Future work
- exempted construction operations 1.8.7
-
Hong Kong
- adjudication in 7.7
- Human Rights Act
- Hybrid contracts
-
ICC contracts
- adjudication provisions 9.4
-
IChemE contracts
- adjudication provisions 9.6
- Insolvency
-
Inspection
- failure to carry out site inspection 4.12.8
- Insurance
- Interest
-
Isle of Man
- application of legislation 1.3.3
-
Issue estoppel
- application to adjudication 4.6.3
-
JCT contracts
- adjudication provisions 9.2
-
Judicial review
- in relation to adjudication 6.38.6
-
Jurisdiction
- of adjudicator in relation to conditional payment 10.10
- Jurisdictional challenge
-
Kitchen sink
- adjudications 2.15.6
-
Latham, Sir David
- Report 1.2.1
-
Law of contract
- and relevant statutory scheme 1.15.6
-
Lien
- for fees and expenses 5.6.5
-
Limitation
- period of 6.42.3
-
Page 626
- exempted construction operations 1.8.8
-
Meeting
- failure to hold 4.12.8
-
Malaysia
- adjudication in 7.5
-
Manitoba
- adjudication in 7.6.6
-
Natural justice
- adjudicator's experience as advocate 4.11.7
- adjudicator obtaining legal advice 4.11.13
- adjudicator's own knowledge and experience 4.11.6
- approaches to two rules 4.11.12
- basic procedural principles 4.11.1
- consideration of evidence and law 4.12
- consideration of evidence under investigative jurisdiction 4.12.1
- constraints upon adjudicators 4.11.11
- declining to consider evidence 4.12.2
- declining to consider late material 4.12.6
- expressing preliminary view 4.12.9
- extensions of time 4.5.3
- failure to ask for further submissions 4.12.13
- failure to carry out site inspection 4.12.8
- failure to consider document 4.12.12
- failure to consider issue 4.12.11
- failure to hold meeting 4.12.7
- failure to warn of potential effect of absence of oral evidence 4.12.3
- failure to warn of potential effect of non-production of documents 4.12.4
- frolic of adjudicator's own 4.11.8
- having regard to a provision not relied upon by parties 4.12.10
- information from other sources 4.11.2
- necessity for material difference to outcome 4.11.9
- new issues and information 4.11.5
- no obligation to accept submission of one party or other 4.11.4
- ‘splitting the difference’ 4.11.10
- summary of law in adjudication cases 4.11.8
- use of alternative approach 4.11.3
- use of witness statement not received by other party 4.12.14
-
NEC 4 Contracts
- adjudication provisions 9.3
-
New Brunswick
- adjudication in 7.6.7
- New South Wales
-
New Zealand
- adjudication in 7.3
-
Nikko
doctrine
- application to adjudication 11.2.1.3
-
Nominating bodies
- for adjudicators 3.6
-
Northern Ireland
- application of legislation to 1.3.2
-
Northern Territory
- adjudication in 7.2.18
- Notice of intention to refer
-
Nova Scotia
- adjudication in 7.6.2
-
Offers
- and costs on enforcement 6.36.8
-
Ontario
- adjudication in 7.6.1
-
Orders for sale
- on enforcement 6.36.3
-
Partial compliance with statutory requirements
- effect 1.15.1
-
Party
- wrong, as a defence 6.11
-
Pay now, argue later
- origin and application 1.2.3
-
Payment
- adjudicator's jurisdiction in absence of certificate 10.10.2
- adjudicator's jurisdiction in relation to conditional payment 10.10
- amount of interim payment 10.5.1
- certificate a condition precedent 10.10.1
- certificates 10.1.2
- conditional payment provisions under the Act 10.4
- conditional payment provisions under the Statutory Scheme 10.7
- effect of non-compliance with requirements for payment notices 10.2.3
-
Page 627
- effect of payee's insolvency 10.3.6
- hybrid contracts 10.2.4
- payee's notice where no payer's or specified person's notice 10.2.5
- payer or qualified person to give notice to payee 10.2.1
- payment in accordance with adjudication decision 10.3.5
- payment notices under the Act 10.2
- payment notices and notices of intention to pay less under the Statutory Scheme 10.6
- payment of notified sum and pay less notices 10.3.2
- payment of notified sum under the Act 10.3
- requirements for payment notices 10.2.2
- requirement for stage payments 10.1.1
- right to suspend performance for non-payment 10.8
- significance of due date for 2.8
- stage payments and dates for payment under the Statutory Scheme 10.5
- time for payment in decision 5.5.7
- timing and effect of pay less notices 10.3.3
- true value adjudication 10.3.4
- when payment becomes due 10.5.2
- withholding notices and pay less notices 10.3.1
-
PFI agreements
- excluded construction contracts 1.13.2
- Plant
-
Power generation
- exempted construction operations 1.8.5
-
Prevarication and procrastination
- difference between 2.8
-
Procedural requirements
- following appointment of adjudicator 4.1
-
Recovery of sums paid
- and limitation 6.42
- Referral
- Referral Notice
-
Repayment on final determination
- on final determination 6.42.1
-
Republic of Ireland
- adjudication in 7.1
-
Repudiation of contract
- effect of on adjudication 2.2.2
-
Reservation of position
- general reservations 6.31.4
-
Res judicata
- application to adjudication 4.6.1
-
Restraining adjudication
- generally 6.38.4
- Remuneration of adjudicator see Fees and expenses
-
Right question
- application of Nikko doctrine to adjudication 11.2.1.3
-
Rule 4.90 of Insolvency Rules 1986 (rule 14.25 of Insolvency Rules 2016)
- as defence to enforcement 6.12.1
- Rules
-
Saskatchewan
- adjudication in 7.6.3
-
Service out of the jurisdiction
- for enforcement 6.5
- Set-off on enforcement
- Severability of decision
-
Silence
- in relation to dispute 2.9
-
Singapore
- adjudication in 7.4
-
Page 628
-
South Australia
- adjudication in 7.2.20
-
Stage Payments
- requirement for 10.1.1
-
Statutory demand
- and enforcement 6.3.3
-
Stay for arbitration
- of enforcement 6.2.4
- Stay of execution on enforcement
-
Stay of proceedings
- pending adjudication 6.39
- Structure
- Summary judgment
-
Taking the initiative
- in ascertaining facts and law 4.11
-
Tasmania
- adjudication in 7.2.21
-
Technology and Construction Bar Association (TECBAR)
- adjudication rules 9.7.1
- Technology and Construction Court
- Technology and Construction Solicitors’ Association (TECSA) rules
- Third Parties
-
Time for payment under decision
- whether needed to be specified 5.5.7
- Time limit for decision
-
True value adjudication
- meaning 10.3.4
- ‘Under the contract'
- Unfair contract terms in consumer contracts
-
Victoria
- adjudication in 7.2.9
- Waiver, agreement and reservation of position
-
West Coast Model
- for adjudication in Australia 7.2.4
-
Western Australia
- adjudication in 7.2.15
-
Winding-up petition
- in relation to enforcement 6.12.7
- Withdrawal of claim
-
Withholding notices
- and pay less notices 10.3.1
-
Wrong party
- as defence to enforcement 6.11