ELEMENTS (EUROPE) LTD v FK BUILDING LTD
[2023] BLR Plus 24
KING’S BENCH DIVISION (TECHNOLOGY AND CONSTRUCTION COURT)
Before Mr Justice Constable
Summary judgment of adjudicator's decision - Whether court should consider parallel Part 8 claim seeking determination of point of contract construction - Time for submitting interim application for payment - Meaning of phrase "not later than four days prior to" - Whether payment application had to be submitted within working hours or by the end of the calendar day.