Building Law Monthly
Adjudication and "conclusive evidence" clauses
Battersea Project Phase 2 Development Company Ltd v QFS Scaffolding Ltd [2024] EWHC 591 (TCC)
In
Battersea Project Phase 2 Development Company Ltd v QFS Scaffolding Ltd [2024] EWHC 591 (TCC), Mr Alexander Nissen KC, sitting as a Judge of the High Court, held, as a matter of interpretation of
the contract between the parties, that the fact that an adjudication had become a nullity as a result of a failure to comply
with the contractually agreed timetable did not mean that there had been a "conclusion" to the adjudication proceedings between
the parties. A "conclusion" required either a decision, award or judgment or a settlement. On the facts, the conclusion of
the adjudication was held to have taken place when the adjudicator reached his decision. This had the consequence that the
Final Payment Notice, which in other circumstances was agreed to be "conclusive" of the amount to be paid, had to be read
subject to the decision of the adjudicator so that the decision of the adjudicator was enforceable and it was not the case
that the Final Payment Notice was conclusive of the matters set out within it.