Causation loss and damage in claims against construction professionals

  • Introduction 113
  • Section A: the essential approach 114
  • Section B: scope of duty 114
  • Section C: remoteness 116
  • Section D: causation 118
    • Effective cause 118
    • Break in the chain of causation 119
    • Outcome dependent upon hypothetical actions 120
  • Section E: assessment of loss 122
    • Costs of rectification or diminution in value? 122
    • Other expenditure or costs 124
    • Liability to third parties 125
    • Personal injury, inconvenience and distress 126
    • The construction professional’s fees 127
  • Section F: mitigation 128
  • Section G: limitation of actions 129
  • Section H: contributory negligence 132
  • Section I: contribution 134

Introduction

6.1 A construction professional may have acted in breach of contractual and tortious duty without causing the person to whom that duty was owed any loss. Indeed, although a breach of contractual duty will always amount to “liability” even if it results in no damage,1 there is no breach of tortious duty unless damage is caused, “damage” being an essential ingredient of the tort of negligence.

The rest of this document is only available to i-law.com online subscribers.

If you are already a subscriber, click Log In button.

Copyright © 2024 Maritime Insights & Intelligence Limited. Maritime Insights & Intelligence Limited is registered in England and Wales with company number 13831625 and address 5th Floor, 10 St Bride Street, London, EC4A 4AD, United Kingdom. Lloyd's List Intelligence is a trading name of Maritime Insights & Intelligence Limited.

Lloyd's is the registered trademark of the Society Incorporated by the Lloyd's Act 1871 by the name of Lloyd's.